Key Facts

Freeboard requirement
2 feet above base flood elevation
Applies to
New construction & substantial improvements
No-BFE fallback
2 feet above highest adjacent grade
Certification deadline
21 days after lowest floor set
Enforcing official
City floodplain administrator
Penalty
Up to $100/day, 30 days jail

Summary

Wilmington requires the lowest floor of any new or substantially improved structure in a special flood hazard area, residential or nonresidential, to sit at least two feet above the base flood elevation, the freeboard that sets the citywide regulatory flood protection elevation. Sec. 18-660(b) lets nonresidential buildings in A zones floodproof instead of elevate, with engineer certification.

(a)Residential construction. All new construction or substantial improvement of any residential structure (including manufactured homes) shall have the lowest floor, including basement, elevated to at least two (2) feet above base flood elevation. Should solid foundation perimeter walls be used to elevate a structure, openings sufficient to facilitate the unimpeded movement of floodwaters shall be provided.(b)Nonresidential construction. New construction or substantial improvement of any commercial, industrial, or nonresidential structure shall have the lowest floor, including basement, elevated at least two (2) feet above the base flood elevation. Structures located in "A" zones may be flood proofed in lieu of elevation provided that all areas of the structure below the required elevation are watertight with walls substantially impermeable to the passage of water, using structural components having the capability of resisting hydrostatic and hydrodynamic loads and the effect of buoyancy.

Full Breakdown

Sec. 18-660 of the floodplain management article applies once FEMA has published base flood elevation (BFE) data for a site. New construction and substantial improvements of residential structures, including manufactured homes, must have the lowest floor, including any basement, elevated to at least two feet above the BFE; that two-foot margin is the city's freeboard, which combines with the BFE to set what the ordinance defines as the regulatory flood protection elevation (Sec. 18-812). If a builder uses solid foundation perimeter walls to reach that elevation, the walls must include openings that let floodwaters move through instead of pooling against the foundation.

Nonresidential buildings, commercial and industrial structures, face the identical two-foot-above-BFE floor elevation, but Sec. 18-660(b) gives them an alternative: a structure in an A zone may be floodproofed rather than elevated if every area below the required elevation is watertight, with walls substantially impermeable to water and structural components engineered to resist hydrostatic and hydrodynamic loads and buoyancy. A registered professional engineer or architect must certify that the floodproofed design meets the standard, and that certification goes to the floodplain administrator under Sec. 18-646(b) before the city signs off.

Where no BFE has been published for a site, Sec. 18-663 falls back to a flat two feet above the highest adjacent grade. Compliance is checked twice: an elevation or floodproofing certificate is due within 21 days after the lowest floor is set, and a final as-built elevation certificate, with dated photographs, is required before the city issues a certificate of occupancy under Sec. 18-646(c) and (d).

Violations & Fines

Failing to submit the floor-elevation certification within 21 days, or failing to correct deficiencies the floodplain administrator identifies, is grounds for a stop-work order under Sec. 18-648(b), and violating a stop-work order is itself a misdemeanor. Sec. 18-648(g) makes any violation of the floodplain article, including building below the required two-foot freeboard, a Class 1 misdemeanor under G.S. § 143-215.58, punishable by up to $100 per day and up to 30 days in jail, with each day a separate offense.

Frequently Asked Questions

How far above the base flood elevation must my house sit in Wilmington?
Sec. 18-660(a) requires the lowest floor, including any basement, of new construction or a substantial improvement to be elevated at least two feet above the base flood elevation. That two-foot margin is the city's freeboard, and it applies to manufactured homes as well as site-built residential structures.
Can a commercial building floodproof instead of elevating?
Yes, but only in A zones. Sec. 18-660(b) lets a nonresidential structure be floodproofed rather than raised if every area below the required elevation is watertight and engineered to resist hydrostatic and hydrodynamic loads, and a registered engineer or architect must certify the design to the floodplain administrator.
What if FEMA hasn't published a base flood elevation for my lot?
Sec. 18-663 requires the lowest floor to be elevated at least two feet above the highest adjacent grade when no BFE has been established, and construction near certain stream banks is separately restricted unless an engineer certifies no increase in flood levels.

Sources & Official References

Other rules in Wilmington

All Wilmington rules

Compare Wilmington to another location·View the North Carolina environmental rules overview

Get notified when Flood Elevation Requirements in Wilmington, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.