Port Townsend, WA Environmental Rules: Flood Zones (2026)
FEMA flood zone rules in Port Townsend, WA, also called floodplain regulations or special flood hazard area (SFHA) rules, determine flood insurance requirements and elevation standards for new construction.
Key Facts
- Permit
- Floodplain development permit required
- Process
- Type I-A administrative permit
- Administrator
- Planning and community development dept.
- Exemption
- Land verified outside the SFHA
- Enforcement
- Chapter 1.20 PTMC violations process
Summary
Any construction or development in Port Townsend's special flood hazard area needs a floodplain development permit before work starts.
A. Construction or development shall not be undertaken within any area of special flood hazard (SFHA) established in PTMC 16.08.070 without approval under this chapter.
1. For development where no other permit or authorization from the city of Port Townsend is necessary to begin or to accomplish the work, the approval shall be documented by issuance of a floodplain development permit.
An application for floodplain development permit shall be processed according to the procedures for a Type I-A permit as established in Chapter 20.01 PTMC, Land Development Administrative Procedures.
2. For development where some other permit or authorization from the city of Port Townsend is required to begin or accomplish the work, including but not limited to development performed by city departments, the floodplain development approval shall be incorporated in such other permit or authorization.
B. A development project is not subject to the requirements of this chapter if it is located on land that can be shown to be outside of the special flood hazard area based on a review of the flood insurance rate maps or by FEMA approval of a letter of map change.
C. Habitat Assessment – When Required. A development permit application shall include a habitat assessment unless the project is, in its entirety, one of the following activities:
1. Routine maintenance of existing landscaping that does not involve grading, excavation, or filling.
Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 3364, passed May 18, 2026).
Full Breakdown
Port Townsend requires approval under PTMC 16.08 before any construction or development occurs within a mapped special flood hazard area (SFHA). If no other city permit applies, the planning and community development department issues a standalone floodplain development permit processed as a Type I-A land development permit. If another permit already covers the work, the floodplain approval is folded into that permit instead. Projects proven to sit entirely outside the SFHA, per FEMA's flood insurance rate maps or an approved letter of map change, are exempt.
Violations & Fines
The planning director enforces PTMC 16.08 violations under the general code-enforcement provisions of Chapter 1.20 PTMC, covering unpermitted or noncompliant SFHA construction.
Frequently Asked Questions
Do I need a permit to build in Port Townsend's flood zone?
How is the flood zone mapped?
Sources & Official References
Other rules in Port Townsend
Compare Port Townsend to another location·View the Washington environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.