Jessamine County, KY Environmental Rules: Stormwater Management (2026)
Key Facts
- Trigger
- Construction activity disturbing 1 or more acre of land
- Permit gate
- No building, grading or land development permit until chapter is met
- Plan review time
- 21 business days from a complete application
- Design storm
- 80th percentile event, 0.58 inches for Jessamine County
- Performance security
- Estimated construction cost of the approved plan plus 25%
- Appeal of notice of violation
- Written notice within 15 days to the Jessamine County MS4 Committee
Summary
In unincorporated Jessamine County, Kentucky, Chapter 156 sets stormwater performance standards for construction disturbing 1 or more acre. No building, grading or other land development permit is issued until the applicant meets the chapter, which starts with a stormwater management plan filed with the Planning Commission.
(B) To prevent the adverse impacts of stormwater runoff, the JCFC has developed a set of performance standards that must be met at new development sites. These standards apply to any construction activity disturbing 1 or more acre(s) of land. The following activities may be exempt from these stormwater performance criteria: (1) Any logging and agricultural activity which is consistent with an approved soil conservation plan or a timber management plan prepared or approved by the applicable governmental agency. (2) Additions or modifications to existing single-family and duplex structures. (3) Developments that do not disturb more than 1 acre of land provided they are not part of a larger common development plan. ... No property owner or developer shall receive any of the building, grading or other land development permits required for land disturbance activities without first meeting the requirements of this chapter prior to commencing the proposed activity.
Full Breakdown
Chapter 156 of the Jessamine County Code, adopted by Ord. passed 4-30-2013, ties stormwater to the permit process. Section 156.003 applies the chapter to all subdivision or site plan applications unless an exemption or waiver applies, and to land development smaller than 1 acre when it is part of a larger common plan of development. The Fiscal Court (JCFC) performance standards apply to any construction activity disturbing 1 or more acre of land. Listed exemptions include logging and agricultural activity consistent with an approved soil conservation plan or timber management plan, additions or modifications to existing single-family and duplex structures, and developments that do not disturb more than 1 acre and are not part of a larger plan.
Section 156.020 is the gate: no property owner or developer receives any of the building, grading or other land development permits required for land disturbance without first meeting the chapter. The application goes to the Planning Commission with 2 copies of the stormwater management plan, 2 copies of the maintenance agreement and the review fees set by the Fiscal Court. Staff tell the applicant within 21 business days of a complete application whether the plan is approved, and a resubmission restarts a 21 business day clock. A final plan must be signed by a licensed professional engineer.
The design standard is the 80th percentile precipitation event, which the chapter sets at 0.58 inches for Jessamine County. Before final plats are recorded, the Planning Commission requires a letter of credit or subdivision bond payable to the JCFC for the total estimated construction cost of the approved plan plus 25%, released only after as-built plans and an engineer's certification.
A separate Chapter 152 bans illicit discharges and connections into the storm drain system on lands outside Wilmore and Nicholasville, with a notice of violation appealable within 15 days of the notice.
Violations & Fines
Section 156.120 makes any violation of the chapter or the approved plan unlawful. The Planning Commission staff issue a written notice of violation, with a stop work order for continuing violations, and can pursue an injunction in Jessamine Circuit Court. Costs and penalties become a lien collectible with the property tax bill. The criminal penalty line in Section 156.999 is printed with its dollar and day amounts blank.
Frequently Asked Questions
When does a project in unincorporated Jessamine County need a stormwater plan?
Who reviews the stormwater plan and how long does it take?
What security does the county require for stormwater practices?
How does a property owner appeal a stormwater notice of violation?
Sources & Official References
Other rules in Jessamine County
Compare Jessamine County to another location·View the Kentucky environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.