Prince George's County, MD Environmental Rules: Stormwater Management (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Core rule
No development without stormwater plan
Design standard
ESD to maximum extent practicable
Max fine
$10,000 per violation
Max jail time
1 year per violation
Appeal deadline
10 days to Board of Appeals

Summary

Prince George's County bars anyone from developing or redeveloping land without meeting the Stormwater Management Ordinance's runoff controls. The Department of Permitting, Inspections and Enforcement requires environmental site design to the maximum extent practicable before allowing any structural best-management practice, and violators face up to $10,000 in fines per offense.

These county ordinances apply to unincorporated areas of Prince George's County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

No person shall develop or redevelop any land without having met the provisions of this Division by providing appropriate stormwater management measures that control or manage runoff, except as provided within Section 32-174 of this Division. ... Planning techniques, nonstructural practices, and design methods specified in the Maryland Design Manual and the Prince George's County Design Manual shall be used to implement ESD to the MEP. The use of ESD planning techniques and treatment practices must be exhausted before any structural BMP is implemented. ... Any person convicted of violating the provisions of this Division shall be guilty of a misdemeanor, and upon conviction thereof, shall be subject to a fine of not more than Ten Thousand Dollars ($10,000.00), or imprisonment not exceeding one (1) year, or both, for each violation, with costs imposed at the discretion of the court and not to exceed Fifty Thousand Dollars ($50,000.00).

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 2026 Update 2).

Full Breakdown

Section 32-173 sets the ordinance's core rule: 'No person shall develop or redevelop any land without having met the provisions of this Division by providing appropriate stormwater management measures that control or manage runoff,' except for the narrow exemptions listed in Section 32-174, such as agricultural practices, additions that disturb less than 5,000 square feet, and work inside the City of Bowie's own approved stormwater system.

Section 32-170(b) explains the goal behind the requirement: using environmental site design (ESD) 'to the maximum extent practicable (MEP)' so that, after development, runoff behaves as close as possible to predevelopment conditions, reducing stream erosion, pollution, siltation and local flooding, and complying with the County's federal Clean Water Act NPDES municipal stormwater permit.

Section 32-178(a)(1) requires that planning techniques, nonstructural practices and design methods from the Maryland and County Design Manuals be used to implement ESD to the MEP, and specifies that 'the use of ESD planning techniques and treatment practices must be exhausted before any structural BMP is implemented.' A concept plan and a stormwater management design plan must be submitted to the Department of Permitting, Inspections and Enforcement for approval under Section 32-177 before a grading or building permit issues under Section 32-184, and a nonrefundable plan-review fee applies under Section 32-185.

The Department may suspend or revoke a stormwater, grading or building permit under Section 32-186 for noncompliance with an approved plan, and appeals of any violation notice go to the County Board of Appeals within 10 days under Section 32-198.

Violations & Fines

Section 32-199(a) makes any conviction under the Stormwater Management Ordinance a misdemeanor carrying a fine of up to $10,000, up to one year in jail, or both, for each violation, with court costs of up to $50,000 added at the judge's discretion. Section 32-199(b) treats each day a violation continues as a separate offense, and the County Attorney may also seek injunctive relief under Section 32-199(c).

Frequently Asked Questions

Do I need a stormwater management plan to build in Prince George's County?
Almost always. Section 32-173 bars developing or redeveloping land without meeting the ordinance's stormwater controls. Narrow exemptions in Section 32-174 cover agricultural practices, projects disturbing under 5,000 square feet, and small additions to existing single-family homes that stay within Subtitle 27's lot coverage limits, but most other projects need an approved design plan.
What is 'ESD to the MEP' in the County's stormwater rules?
It stands for environmental site design to the maximum extent practicable, the standard Section 32-178(a)(1) requires the Department to apply. Nonstructural techniques such as rain gardens, permeable pavement and reduced impervious area must be used to their fullest extent before a project can turn to a structural facility like a pond or vault.
What happens if I build without the required stormwater approval?
Section 32-199 makes it a misdemeanor punishable by up to $10,000 in fines and up to a year in jail per violation, with each day of continued noncompliance counted as a separate offense. The County Attorney can also go to court for an injunction, and the Department can suspend or revoke the permit under Section 32-186.

Sources & Official References

Other rules in Prince George's County

All Prince George's County rules

Compare Prince George's County to another location·View the Maryland environmental rules overview

Get notified when Stormwater Management in Prince George's County, MD changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.