Solano County, CA Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Threshold
1 acre or more of land disturbance
Required plan
Storm Water Pollution Prevention Plan
BMP standard
Caltrans Storm Water Quality Handbooks
Timing
BMPs installed before grading begins
Enforcing agency
Dept. of Resource Management
Penalty
Misdemeanor, up to $500/day

Summary

Any Solano County grading project disturbing an acre or more must comply with NPDES stormwater rules under Code Section 31-31, including a Storm Water Pollution Prevention Plan with best management practices installed before grading starts.

City-specific rules exist: Vacaville, Vallejo, and Fairfield have their own stormwater management rules that differ from Solano County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

All grading plans and permits with land disturbance equal to or greater than 1 acre shall comply with the provisions of this section for NPDES compliance. No grading and drainage permit shall be issued unless the plans for such work include a Storm Water Pollution Prevention Plan with details of best management practices, including desilting basins or other temporary drainage or control measures, or both, as may be necessary to control construction-related pollutants which originate from the site as a result of construction related activities.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 1868, passed April 9, 2026).

Full Breakdown

Solano County Code Section 31-31 applies National Pollutant Discharge Elimination System (NPDES) requirements to every grading plan and permit covering one acre or more of land disturbance. Before the Department of Resource Management can issue a grading and drainage permit for such a project, the applicant's plans must include a Storm Water Pollution Prevention Plan detailing best management practices, such as desilting basins or other temporary drainage and control measures, sufficient to control construction-related pollutants leaving the site. Section 31-31(b) requires that all best management practices be installed before grading begins, and that they stay maintained in good working order to the Director's satisfaction throughout construction, unless the Director has already granted final grading approval and all permanent drainage and erosion control systems required by the permit are in place.

The standards applicants must follow are drawn from the Storm Water Quality Handbooks, Construction Site Best Management Practices Manual, defined in Section 31-12 as the Caltrans-prepared manual of best conventional and best available technology BMPs consistent with the Clean Water Act. Section 31-26(b) requires major-permit applicants to submit an engineered erosion, sediment and runoff control plan, prepared and sealed by a registered civil engineer, that incorporates the Handbook's recommendations and addresses vegetative measures, drainage protection, sediment control, runoff control, cut and fill construction, and dust control. Section 31-30(j) separately requires that runoff from impervious surfaces created by grading be treated with biofiltration, or another Director-approved alternative, before it leaves the property or enters any state or federal waters. Section 31-30(i) further requires that any development creating more than 5,000 square feet of new impervious surface retard post-development runoff to no more than predevelopment rates using structural or vegetative measures maintained annually.

Because these BMP and NPDES obligations attach to the grading and drainage permit itself, the Department of Resource Management enforces them alongside the rest of Chapter 31: a stop-work order can issue under Section 31-42(d) if a project falls out of compliance with its approved erosion and sediment control plan, and the Director may require remedial work at the applicant's expense under Section 31-42(g) to protect completed work or prevent further damage.

Violations & Fines

Failing to install or maintain required best management practices, or grading without the NPDES-compliant Storm Water Pollution Prevention Plan required for disturbances of an acre or more, is enforced as a Chapter 31 violation. Under Section 31-44(c) noncompliance is a misdemeanor punishable by a fine of not more than $500 for each day the violation continues, and the violator is strictly liable for the County's costs of abating any resulting erosion, sediment or runoff hazard. The Director may also issue a stop-work order under Section 31-42(d) until compliance with the approved plan is restored.

Frequently Asked Questions

When does a Solano County project need an NPDES stormwater plan?
Section 31-31 requires NPDES compliance for any grading plan or permit covering an acre or more of land disturbance. The applicant must submit a Storm Water Pollution Prevention Plan with best management practices before the county will issue the grading and drainage permit.
What best management practices standard does Solano County use?
Section 31-12 points applicants to the Caltrans Storm Water Quality Handbooks, Construction Site Best Management Practices Manual, which sets best conventional and best available technology practices consistent with the federal Clean Water Act.
Can grading continue if stormwater controls fail?
No. Section 31-31(b) requires BMPs to stay maintained in good working order throughout construction, and Section 31-42(d) allows the Director to issue a stop-work order if the project falls out of compliance with its approved erosion and sediment control plan.

Sources & Official References

Other rules in Solano County

All Solano County rules

California rules heatmap·Compare Solano County to another location·View the California environmental rules overview

Get notified when Stormwater Management in Solano County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Stormwater Management in Cities Across Solano County