Stafford County, VA Environmental Rules: Stormwater Management (2026)
Key Facts
- Governing section
- § 11-6.5, Stormwater management plan
- Applies to
- entire common plan of development, not per lot
- Design manual
- Stafford County Stormwater Management Design Manual
- Small-project shortcut
- 2,500-10,000 sq ft, licensed professional certifies
- Permit fee range
- $290.00 to $14,300.00 (Table 1)
Summary
Stafford County requires a stormwater management plan for regulated land-disturbing activity, applying the technical criteria across an entire common plan of development rather than lot by lot. The plan must cover surface runoff and converted groundwater flows and be approved by the VESMP authority before construction.
(a)A stormwater management plan shall be developed and submitted to VESMP authority. The stormwater management plan shall be implemented as approved or modified by VESMP authority and shall be developed in accordance with the following:(1)A stormwater management plan for a land-disturbing activity shall apply the stormwater management technical criteria set forth in this article and Article 4 (9VAC25-875-670 et seq.) of Part V of the Regulation to the entire land-disturbing activity. Individual lots in new residential, commercial, or industrial developments, including those developed under subsequent owners, shall not be considered separate land-disturbing activities and therefore must be considered in the common plan of development.(2)A stormwater management plan shall consider all sources of surface runoff and all sources of subsurface and groundwater flows converted to surface runoff.
Full Breakdown
5 of the county's Virginia Erosion and Stormwater Management Program spells out what a stormwater management plan must do: it applies the technical criteria in Part V of the state regulation (9VAC25-875) to the entire land-disturbing activity, and individual lots inside a new residential, commercial, or industrial development, even lots sold to a later owner, cannot be treated as separate projects for compliance purposes. The plan has to account for every source of surface runoff plus subsurface and groundwater flows that get converted into surface runoff.
A complete submission needs background information on discharge points, owner and parcel contact details, a site condition narrative, a description of the proposed stormwater facilities, hydrologic and hydraulic computations built to the Stafford County Stormwater Management Design Manual, a topographic site map showing drainage areas, floodplains, and FEMA panel references, and, where the operator plans to buy nutrient credits, a letter of availability from the offsite provider. Plans requiring a professional license must carry the seal of a Virginia-licensed engineer, architect, landscape architect or land surveyor.
For smaller residential work, such as accessory structures, sidewalks, pools or patios disturbing between 2,500 and 10,000 square feet that add no more than 10 percent impervious cover and need no water-quality controls, a licensed professional may certify a simplified plan instead. 00 for construction disturbing 100 acres or more, under Table 1 of Section 11-16.
Violations & Fines
Operating without an approved stormwater management plan exposes the owner to a stop-work order and civil penalties of up to $32,500.00 per violation under Stafford County Code § 11-13, with each day treated as a separate offense. Willful or negligent noncompliance is also a misdemeanor carrying up to 12 months in jail and a fine between $2,500.00 and $32,500.00.
Frequently Asked Questions
Does Stafford County require a stormwater plan per lot?
Who has to seal a Stafford County stormwater plan?
Is there a simplified stormwater option for small residential projects?
Sources & Official References
Other rules in Stafford County
Compare Stafford County to another location·View the Virginia environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.