Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit issuer
Dept. of Planning and Zoning
Triggers permit
New, altered, replaced fence/wall
Removal threshold
Over 400 feet needs a permit
Work must start
Within 30 days of issuance
Work must finish
Within 120 days of issuance

Summary

Annapolis requires a Department of Planning and Zoning permit before erecting, altering, replacing, or removing more than 400 feet of an existing fence or wall, with a scaled site drawing and construction details due at application.

No new fence or wall shall be erected, placed, or maintained, and no existing fence or wall shall be altered or replaced, and no existing fence over 400 feet in length shall be removed or demolished until a complete application is submitted and a permit is obtained from the Department of Planning and Zoning.

Source: Annapolis Permits and InspectionsView official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 2025 Update 2).

Full Breakdown

City Code § 17.34.010 bars erecting, placing, maintaining, altering, or replacing any fence or wall, and removing more than 400 feet of an existing fence, until a complete application is submitted and a permit is issued by the Department of Planning and Zoning. The application must include a scaled drawing showing the proposed location, dimensions, relationship to property lines, existing structures, trees over five inches in diameter within three feet, and steep topography, plus construction drawings or photos of the design and materials. Work must start within 30 days of issuance and finish within 120 days, or the Director revokes the permit. Fences must also meet the standards in Zoning Code § 21.60.070.

Violations & Fines

Building, altering, or removing a fence without the required permit, or missing the 30-day start or 120-day completion deadlines, is a municipal infraction under § 17.34.030: a civil fine, with each day the violation continues a separate offense.

Frequently Asked Questions

Do I need a permit to replace an existing fence in Annapolis?
Yes. City Code § 17.34.010 requires a Planning and Zoning permit to alter or replace any fence or wall, not just build a new one.
How long do I have to build once the permit is issued?
Work must start within 30 days and be finished within 120 days of issuance, or the Director revokes the permit.

Sources & Official References

Other rules in Annapolis

All Annapolis rules

Compare Annapolis to another location·View the Maryland fence regulations overview

Get notified when Fence Permit Requirements in Annapolis, MD changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.