St. Peters, MO Fence Regulations: Fence Permit Requirements (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

No-permit districts
R-1, R-1A, R-2, R-4, A-1
Permit required
R-3, Commercial, and Industrial districts
Permit fee cap
$50 building permit
Electric fence exemption
Exempt under RSMo Section 67.301
Governing section
Municipal Code Section 405.360(B)(1), (F)(1)

Summary

In the City of St. Peters, Missouri, no permit is required to build, alter, or replace a fence in most residential and agricultural districts. Section 405.360(F)(1) reverses that default for multi-family "R-3" developments, commercial "C" districts, and industrial "I" districts, where a building permit capped at fifty dollars must be obtained before the fence goes up.

1. No permit shall be required for the erection, installation or alteration of any fence within the City of St. Peters except as otherwise required in this Section. ... ... F. Fence Permit In All "R-3", "C" (Commercial) And "I" (Industrial) Districts. 1. For all fences installed within an "R-3(A)", "R-3(8)", a multiple-family development within a Planned Urban District (PUD), "C", or "I" District, a building permit, not to exceed fifty dollars ($50.00), shall be obtained prior to installation of the fence.

Full Breakdown

Section 405.360(B)(1) sets the City's baseline rule: no permit is required for erecting, installing, or altering any fence within the City of St. Peters, except as otherwise required elsewhere in the same Section. Subsection F carves out that exception. For any fence installed within an "R-3(A)" or "R-3(B)" multiple-family district, a multiple-family development inside a Planned Urban District, a "C" Commercial district, or an "I" Industrial district, Section 405.360(F)(1) requires a building permit before the fence is installed, and caps the permit fee at fifty dollars.

Electrified fences are carved out of even that permit requirement under Missouri Statute Section 67.301, RSMo, but the property owner must still meet City rules on aesthetics, access to public rights-of-way, sidewalks, and utility easements, structural soundness, and drainage impact. Wherever a permit applies or not, the same general standards in Subsection B still govern: fences are capped at six feet unless a district rule says otherwise, must be finished within six months of the start of construction, must be kept in good condition with damaged boards replaced and rust removed, and may not be electrified except as Missouri Statutes 67.301 and 67.494 allow. The Planning, Community and Economic Development Department administers fence permits and enforces these standards through its Neighborhood Preservation code enforcement staff.

Violations & Fines

Building a fence without the required permit in an "R-3," "C," or "I" district, or otherwise violating Section 405.360, is an ordinance violation under Section 405.815 of the St. Peters Municipal Code. A first offense is punishable by a fine of ten to two hundred fifty dollars per day the violation continues, or up to ten days in jail, or both; repeat violations at the same address raise the fine to one hundred to five hundred dollars per day.

Frequently Asked Questions

Do I need a permit to put up a fence in St. Peters?
Generally no. Section 405.360(B)(1) of the St. Peters Municipal Code says no permit is required to erect, install, or alter a fence in the City, except where the Section says otherwise. That exception covers "R-3" multi-family, commercial, and industrial districts, not ordinary single-family and two-family residential lots.
Which districts actually require a fence permit?
Section 405.360(F)(1) requires a building permit for fences in an "R-3(A)" or "R-3(B)" multiple-family district, a multi-family development inside a Planned Urban District, a "C" Commercial district, or an "I" Industrial district. Fences in R-1, R-1A, R-2, R-4, and A-1 districts stay permit-free under the general rule in Subsection B.
How much does the St. Peters fence permit cost?
The building permit required under Section 405.360(F)(1) is capped at fifty dollars, and must be obtained before the fence is installed. Electrified fences skip this permit entirely under Missouri Statute Section 67.301, though they still have to meet the City's aesthetic, right-of-way, structural, and drainage standards.
What happens if I skip a required fence permit?
Installing a fence in a district that requires the Section 405.360(F)(1) permit without obtaining it is an ordinance violation under Section 405.815, punishable by a fine of ten to two hundred fifty dollars for each day the violation continues, or up to ten days in jail, or both.

Sources & Official References

Other rules in St. Peters

All St. Peters rules

Compare St. Peters to another location·View the Missouri fence regulations overview

Get notified when Fence Permit Requirements in St. Peters, MO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.