Monroe Township (Gloucester County), NJ Fence Regulations: Retaining Walls (2026)
Key Facts
- Engineer review trigger
- Retaining walls over three feet in height
- Grading near property line
- None within five feet unless needed for drainage
- Permit fee, over 550 sq ft
- $210 for Class III structures
- Permit fee, 550 sq ft or less
- $106 for Class III structures
- Lot grading waiver
- $50 determination fee
- Certificate of occupancy
- Withheld until the as-built plan is approved
Summary
In Monroe Township, Gloucester County, New Jersey, a retaining wall over three feet in height on a residential lot must be designed and then reviewed and approved by the Engineer under § 175-117.1(F)(9) of the Township Code. Construction permit fees for retaining walls are set in § 104-18.
F. Performance standards. ... (1) All grading shall be done in a manner that will result in a no adverse impact to adjacent properties. ... (9) Retaining walls over three feet in height must be designed and then reviewed and approved by the Engineer. ... (12) The permittee may request a waiver of a particular performance standard upon presentation of a reasonable justification. The Engineer shall have the authority to review the request and issue an administrative change, provided it does not violate the intent of the ordinance.
Full Breakdown
The wall rule sits in § 175-117.1, Lot grading and drainage, among the performance standards in Subsection F. Subsection F(9) says retaining walls over three feet in height must be designed and then reviewed and approved by the Engineer. The section applies to the development of all lots in the Township for residential purposes, which covers construction, reconstruction or relocation of a residential structure, an enlargement or accessory structure with a land disturbance of 500 square feet or more, and an in-ground swimming pool.
The grading standards around the wall are specific. No grading can occur within five feet of a property line unless necessary to direct drainage off or onto the property, slopes cannot be steeper than three horizontal to one vertical, and the top of block elevation must be a minimum of six inches above the highest adjacent grade. The lot grading plan must be signed and sealed by an engineer licensed by the State of New Jersey, and any proposed impervious surface within five feet of a property line needs a lot grading waiver application. The determination of a waiver costs $50.
Under Subsection F(12), the permittee can request a waiver of a particular performance standard with reasonable justification, and the Engineer can issue an administrative change if it does not violate the intent of the ordinance. Fees are set in Chapter 74, Fees. For developments, the applicant deposits a performance escrow of $2,000 per lot up to 25 lots plus an inspection escrow of $650 per dwelling unit.
Separately, § 104-18(C)(1)(a) sets the construction permit fee for retaining walls greater than 550 square feet associated with a Class III structure at $210, and $106 for walls of 550 square feet or less. Retaining walls in other than Class III structures are based on cost of construction. Section 144-77 adds that retaining walls involving fill in floodways must meet § 144-36A and N.J.A.C. 7:13.
Violations & Fines
Section 175-117.1 prints no fine of its own. Its enforcement lever is the certificate of occupancy: under Subsection E a certificate of occupancy shall not be issued until the permittee submits an accurate final survey (as-built plan) that the Engineer approves as showing the lot grading in substantial conformance with the approved plan.
Frequently Asked Questions
Does a retaining wall in Monroe Township need an engineer?
What does a retaining wall permit cost in Monroe Township?
Can I grade right up to my property line behind a wall?
Can a standard in the lot grading rules be waived?
Sources & Official References
Other rules in Monroe Township (Gloucester County)
Compare Monroe Township (Gloucester County) to another location·View the New Jersey fence regulations overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.