Key Facts

Named provision
Floodway retaining walls, § 90-26(c)
Floodway fill limit
No increase in base flood elevation
Analysis required
Sealed by Florida licensed engineer
Reviewed by
Floodplain administrator (city engineer)
Outside floodways
No separate height/setback rule printed

Summary

Ocala only singles out retaining walls where they cross into a regulated floodway: City Code § 90-26(c) requires any retaining wall, sidewalk or driveway that places fill in a floodway to meet the same limits as other floodway fill under § 90-22(d). That means a floodway encroachment analysis, sealed by a Florida licensed engineer, must show the wall will not raise the base flood elevation before the floodplain administrator can permit it.

(c)Retaining walls, sidewalks and driveways in regulated floodways. Retaining walls and sidewalks and driveways that involve the placement of fill in regulated floodways shall meet the limitations of subsection 90-22(d). ... (d)Limitations on sites in regulatory floodways. No development, including but not limited to, site improvements, and land disturbing activity involving fill or regrading, shall be authorized in the regulatory floodway unless the floodway encroachment analysis required in subsection 90-15(c)(l) demonstrates that the proposed development or land disturbing activity will not result in any increase in the base flood elevation. ... Violation of the provisions of this chapter or failure to comply with any of its requirements, including violation of conditions and safeguards established in connection with granting of variances or special exceptions shall be subject to the jurisdiction of the city's municipal code enforcement board or special magistrate under chapter 36 of this Code. Each day such violation continues shall be considered a separate offense.

Full Breakdown

The Code of Ordinances does not set a citywide height limit or standalone permit article for retaining walls; the only provision naming them sits in Chapter 90's floodplain regulations. Section 90-26, titled "Other development," covers structures the rest of the floodplain chapter does not address by name, and subsection (c) calls out "Retaining walls, sidewalks and driveways in regulated floodways" specifically: any of those features that involve placing fill within a mapped regulatory floodway must meet the limitations set in § 90-22(d). That cross-referenced subsection is strict about floodway fill generally: no development, including site improvements and land-disturbing activity involving fill or regrading, can be authorized in a regulatory floodway unless a floodway encroachment analysis required under § 90-15(c)(1) demonstrates the work will not increase the base flood elevation at all.

That analysis has to be prepared, signed and sealed by a Florida licensed engineer using standard engineering methods and models, and it has to accompany the site plan and construction documents submitted with the floodplain development permit application under § 90-14. The floodplain administrator, the city engineer under § 90-13, reviews that analysis before issuing the permit, and if a proposed retaining wall would raise base flood elevations, the applicant instead has to pursue a conditional letter of map revision from FEMA before the city can act on it.

Outside a mapped regulatory floodway, a retaining wall still falls under Ocala's general building permit requirement in § 82-40(a) for any construction, addition or alteration, but the code does not print a separate height, setback or engineering standard for retaining walls outside that floodway-specific rule.

Violations & Fines

Placing fill for a retaining wall, sidewalk or driveway in a regulated floodway without the § 90-15(c)(1) encroachment analysis, or without the floodplain administrator's permit under § 90-14, violates § 90-26(c) and § 90-22(d). Under § 90-18, that is treated as a violation of Chapter 90 enforceable through stop-work orders and referral to the city's code enforcement board or special magistrate, with each day the noncompliant wall remains a separate offense.

Frequently Asked Questions

Does Ocala limit the height of a retaining wall?
The Code of Ordinances does not print a citywide height limit for retaining walls. The only section that names them, § 90-26(c), applies only inside a mapped regulatory floodway, where the wall must meet the fill limitations in § 90-22(d) rather than a fixed height standard.
Do I need an engineer for a retaining wall in Ocala?
If the wall sits in a regulated floodway and involves placing fill, yes: § 90-22(d) requires a floodway encroachment analysis under § 90-15(c)(1), prepared and sealed by a Florida licensed engineer, showing the wall will not raise the base flood elevation before the floodplain administrator can permit it.
Who approves a retaining wall permit in a floodway in Ocala?
The floodplain administrator, the city engineer under § 90-13(a), reviews the floodway encroachment analysis and issues the floodplain development permit under § 90-14 before floodway retaining wall construction can begin.
What if my retaining wall is not near a floodway?
Section 90-26(c) and the floodway fill limits only apply inside a regulated floodway. A retaining wall elsewhere in Ocala still needs the general building permit required under § 82-40(a) for construction, but the code does not print a separate retaining-wall-specific height or engineering standard outside the floodway.

Sources & Official References

Other rules in Ocala

All Ocala rules

Florida rules heatmap·Compare Ocala to another location·View the Florida fence regulations overview

Get notified when Retaining Walls in Ocala, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.