Film location permits in Benton County, OR, sometimes called film shoot permits, production permits, or filming authorizations, cover commercial photography, video shoots, and motion picture production.

Key Facts

Threshold
45 days or less is a permitted use
Ministerial cite
BCC 55.105(12)
Over 45 days
Conditional use permit required
Reviewer
Planning Official, BCC 55.205(16)
Excluded
Editing/marketing facilities need home occupation
Fine
$500 per violation, $1,000 continuing

Summary

Filming on farmland in unincorporated Benton County splits on a 45-day line. On-site filming and its accessory activities that run 45 days or less in the Exclusive Farm Use Zone are a permitted use under BCC 55.105(12), and the County's sign-off on that use is not a land use decision. Cross the 45-day mark, or leave sets standing past 45 days, and the shoot needs a conditional use permit from the Planning Official under BCC 55.205(16).

These county ordinances apply to unincorporated areas of Benton County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(12)On-site filming and activities accessory to onsite filming for 45 days or less. A decision of the County issuing any permits necessary for activities under this provision is not a land use decision. ... (16)On-site filming and activities accessory to on-site filming that exceed 45 days on any site within a 1-year period or involve erection of sets that would remain in place for longer than 45 days.

Full Breakdown

105(12) makes on-site filming a permitted use as long as it and its accessory activities last 45 days or less on the site. That covers filming and site preparation, set construction, staging, makeup and customary support services, plus production of advertisements, documentaries, feature films and television series that rely on the rural character of the EFU zone. It does not cover marketing or editing facilities, which can only be sited as a home occupation, or new construction that itself needs a building permit. Because a permit decision under this ministerial provision is not defined as a land use decision, it does not trigger the notice and hearing procedures of BCC Chapter 51.

215, which weighs whether the extended shoot will force a change in accepted farm practices or raise their cost on surrounding farmland. Productions planning a long location shoot, or a set that will stand for more than 45 days, should apply before filming starts rather than after the clock runs out.

Violations & Fines

Filming past the 45-day threshold without the BCC 55.205(16) conditional use permit is an ordinary County Code violation, processed like any other under BCC Chapter 31: enforcement officers move from a verbal notice through a written notice of violation, a notice to comply, and a stop-work order before referring the matter for an infraction complaint. Under BCC 31.125(3), the County may seek a $500 fine per violation and $1,000 for a continuing violation, with each day counted separately.

Frequently Asked Questions

Do I need a permit to film in the Exclusive Farm Use Zone in Benton County?
No, as long as the filming and its accessory activities, like set construction and staging, run 45 days or less on that site. BCC 55.105(12) makes short on-site filming a permitted use in the Exclusive Farm Use Zone, and the County's authorization for it is not treated as a land use decision.
What if my production needs more than 45 days on the same site?
You need a conditional use permit reviewed by the Planning Official under BCC 55.205(16), which applies once filming or its sets exceed 45 days on the same site within a one-year period. Approval is judged against BCC 55.215's standard that the use not force a significant change in nearby farm practices.
Can I put an editing suite or office on the farm property during filming?
Editing suites, marketing offices and similar facilities are excluded from the on-site filming permitted use and can only be sited as a home occupation under BCC 91.200 through 91.215, and any new structure built for the production still needs its own building permit under BCC 55.105(12)(b).

Sources & Official References

Other rules in Benton County

All Benton County rules

Compare Benton County to another location·View the Oregon filming & production overview

Get notified when Location Permits in Benton County, OR changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.