Film location permits in Josephine County, OR, sometimes called film shoot permits, production permits, or filming authorizations, cover commercial photography, video shoots, and motion picture production.

Key Facts

Outright use threshold
45 days or less, no permit
Beyond 45 days
Conditional use, § 19.64.040(L)
Review type (over 45 days)
Quasi-judicial, Chapter 19.45 JCC
State authority cited
ORS 215.306
Zones
Exclusive Farm (EF) and Farm Resource (FR)

Summary

In the Exclusive Farm and Farm Resource zones outside the Grants Pass and Cave Junction urban growth boundaries, on-site filming and its accessory activities need no permit at all for 45 days or less under § 19.64.020(C), but once filming runs longer than 45 days it becomes a conditional use under § 19.64.040(L), requiring quasi-judicial review.

These county ordinances apply to unincorporated areas of Josephine County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

C. Filming. On-site filming and activities accessory to on-site filming for 45 days or less as provided for in ORS 215.306. ... L. Filming. ... On-site filming and activities accessory to on-site filming that exceed 45 days, as provided for in ORS 215.306.

Full Breakdown

Section 19.64.020 lists uses allowed outright on farm-zoned land, meaning no permit or authorization is required to conduct them, and subsection (C) places on-site filming and activities accessory to it in that category as long as the filming runs 45 days or less, citing ORS 215.306 as the authorizing statute. The section's own introductory text carves filming out of the structure-permit rule that applies to other outright uses: it specifies that structures placed in conjunction with outright uses need ministerial review and a development permit under Chapter 19.41 JCC, except for film sets authorized under subsection (C), which are exempt from that structure-permit step.

Once a shoot exceeds 45 days, § 19.64.040(L) reclassifies the same activity, on-site filming and its accessory activities, as a conditional use, again citing ORS 215.306. Conditional uses under § 19.64.040 go through quasi-judicial review procedures under Chapter 19.22 JCC, must meet the conditional-use requirements of Chapter 19.45 JCC and site plan review under Chapter 19.42 JCC, and still need a development permit under Chapter 19.41 JCC as final approval, along with the development standards in § 19.64.095. The 45-day line is the only variable between the two provisions; the underlying activity description is identical.

Violations & Fines

Filming operations that run longer than 45 days without obtaining the conditional-use approval § 19.64.040(L) and Chapter 19.45 JCC require are operating outside the outright-use exemption in § 19.64.020(C) and are subject to enforcement as an unpermitted use. Even a short shoot that erects permanent structures beyond a temporary film set must still meet the applicable development standards of § 19.64.095 and secure a development permit under Chapter 19.41 JCC.

Frequently Asked Questions

Do I need a permit to film on farm-zoned land in Josephine County for a few days?
No. § 19.64.020(C) allows on-site filming and its accessory activities for 45 days or less as an outright use in the Exclusive Farm and Farm Resource zones, meaning no permit or authorization is required to conduct the filming itself.
What happens if my shoot runs past 45 days?
§ 19.64.040(L) reclassifies filming and its accessory activities that exceed 45 days as a conditional use, which means quasi-judicial review under Chapter 19.45 JCC and site plan review under Chapter 19.42 JCC, plus a development permit under Chapter 19.41 JCC before the extended shoot can proceed.
Can I build permanent structures for the film set without a permit?
The 45-day outright-use exemption in § 19.64.020 covers the filming activity itself, and the section's own text carves film sets out of the usual structure-permit requirement imposed on other outright uses; anything beyond a temporary set still needs to meet § 19.64.095's development standards.

Sources & Official References

Other rules in Josephine County

All Josephine County rules

Compare Josephine County to another location·View the Oregon filming & production overview

Get notified when Location Permits in Josephine County, OR changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.