Key Facts

Road closure decision
Within ten business days of receipt
Traffic control or stunts tier
Within four business days
Normal permit
Within two business days
Signs and traffic devices
Posted at the applicant's expense
Appeal
Five days, filed with the city clerk

Summary

In the City of Palm Desert, California, a film permit that requires road closures gets the longest review window in Municipal Code § 5.94.070: ten business days from receipt, compared with two business days for a normal permit. The city can also require no parking signs, traffic control devices and public safety staff at the applicant's expense.

A. The application shall be approved or denied within the following time periods: 1. Within two business days of receipt of application for approval and issuance of "normal" permit; 2. Within four business days of receipt of application for approval and issuance of permit requiring traffic control which exceeds three minutes, stunts or special effects; 3. Within ten business days of receipt of application for approval and issuance of permit requiring road closures.

Full Breakdown

Palm Desert sorts film permit applications into three review tiers in § 5.94.070(A). A normal permit is approved or denied within two business days of receipt. A permit requiring traffic control that exceeds three minutes, or involving stunts or special effects, is decided within four business days. A permit requiring road closures is decided within ten business days. The film permit rules are Chapter 5.94 of the Palm Desert Municipal Code.

The application form furnished by the city asks for the location or locations, dates and approximate daily times of the filming, and for the exact number, type and description of all vehicles and equipment to be involved or parked on city streets during filming. Separately, § 5.94.050 requires the application to be filed at least five business days before filming starts, and the city manager can waive that deadline for good cause if there is time left to process the application and for the city to prepare.

Under § 5.94.080 the city can condition a permit on the posting of no parking signs and the placement of other traffic control devices at the applicant's expense. It can require the presence of county sheriff's department, county fire department or city public works department employees when the particular filming activity needs them, also at the applicant's expense, and it can require notice to affected property owners.

A permit must be approved unless the filming will substantially interfere with the operation of emergency vehicles in the proposed permit area, creates a substantial risk of injury to persons or property, rests on an incomplete or materially false application, or would violate federal, state or local law including license or permit requirements. When a ground for denial can be corrected by reasonable conditions, the city imposes conditions rather than denying.

The schedule of fees for city services and use of city property is set by city council resolution and prepaid before the permit issues. Chapter 5.94 does not itself print closure hours, detour distances or a maximum closure length; the time, place and manner terms come through the conditions authorized by § 5.94.080.

Violations & Fines

Filming without a permit is an infraction under § 5.94.150, and the city can also bring a civil action. A permittee who does not follow permit terms, including traffic control conditions, can have the permit revoked by the city manager under § 5.94.130. The permit holder can appeal a denial, a condition or a revocation within five days of the city decision by filing with the city clerk, and the city council hears it at its next regular meeting.

Frequently Asked Questions

How long does Palm Desert take to decide a permit with a road closure?
Ten business days from receipt of the application under § 5.94.070(A)(3). The four-business-day tier covers traffic control longer than three minutes, stunts or special effects, and the two-business-day tier covers a normal permit. The five-business-day filing deadline in § 5.94.050 is a separate requirement.
Who pays for sheriff, fire or public works staff at a closure?
The applicant. Section 5.94.080 lets the city require county sheriff's department, county fire department or city public works department employees to be present when the particular filming activity needs them, and it places that cost on the applicant. The same section puts the cost of no parking signs and traffic control devices on the applicant.
Can the city refuse a permit over emergency vehicle access?
Yes. Section 5.94.070(B) lets the city deny a permit when the filming activity will substantially interfere with the operation of emergency vehicles in the proposed permit area. If reasonable conditions can correct that problem, § 5.94.070(C) requires the city to impose them instead of denying the permit.
Can the film company change its date after approval?
Yes. Under § 5.94.100 the city manager is authorized to change the date of an issued film permit on reasonable notice from the permittee in advance of the filming, without requiring a new application or a new application fee.

Sources & Official References

Other rules in Palm Desert

All Palm Desert rules

California rules heatmap·Compare Palm Desert to another location·View the California filming & production overview

Get notified when Street Closures in Palm Desert, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Street Closures in Nearby Cities

How other cities in Riverside County handle street closures.

Moreno Valley, CA
Some Restrictions
Corona, CA
Significant Restrictions