Skip to main content
CityRuleLookup

Pismo Beach, CA Filming & Production: Street Closures (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Deadline with street closure
Thirty (30) days before the first day of filming
Standard deadline
Fourteen (14) days before filming begins
Closure granted by
City administrator, designee or chief of police, by short-term encroachment permit
Decision time
Two business days unless extensive review is required
Traffic control cost
Signs, devices and monitors at the applicant's expense
Appeal deadline
Five business days after written notice

Summary

In the City of Pismo Beach, California, a film permit application that includes street closures must be filed a minimum of thirty (30) days before filming, against fourteen (14) days otherwise. The applicant requests the closure on the permit application, and the city administrator, a designee or the chief of police grants a short-term encroachment permit.

A. Applications for a film permit must be filed with the film development office a minimum of fourteen (14) days in advance of the date the film activity is to begin, except that those which include street closures, major stunts, or pyrotechnics must be filed a minimum of thirty (30) days in advance of the first day of filming. ... The film permit shall be approved by the film development office unless determined from consideration of the application or other pertinent information, that any of the following conditions exist: 1. The filming activity will substantially disrupt the use of a public right-of-way or street at a time when it is usually subject to traffic congestion, or interfere with the operation of emergency vehicles in the proposed permit area; ... 5.44.140 Street closures. The applicant for a film permit may request that the city authorize a street closure on the film permit application. A short-term encroachment permit shall be granted by the city administrator, his designee or by the chief of police.

Full Breakdown

Street closures for filming in the City of Pismo Beach run through Chapter 5.44 of the Municipal Code. Section 5.44.050 A sets the filing deadline: applications for a film permit must be filed with the film development office a minimum of fourteen (14) days before filming begins, except that applications including street closures, major stunts or pyrotechnics must be filed a minimum of thirty (30) days in advance of the first day of filming. Late applications are not processed unless the film development office finds special circumstances, and the office considers a late filing on a showing of good cause if there is time to investigate and for city staff to prepare (Section 5.44.050 B and D).

Section 5.44.140 lets the applicant request a street closure on the film permit application. A short-term encroachment permit is granted by the city administrator, his designee or the chief of police. The permit decision comes within two business days of receipt unless the filming needs extensive review by other city departments or agencies for public health or welfare concerns or fire or traffic safety (Section 5.44.070 A).

The film development office approves the permit unless it finds a listed ground for denial. The first ground is that the filming will substantially disrupt the use of a public right-of-way or street at a time when it is usually subject to traffic congestion, or interfere with the operation of emergency vehicles in the proposed permit area. Another ground is substantial interference with right-of-way or street maintenance work or a previously authorized excavation permit. Where a ground can be corrected, the office can impose reasonable conditions instead of denying the permit (Section 5.44.070 B).

Conditions under Section 5.44.080 include no-parking signs, traffic control devices and traffic and crowd control monitors at the applicant's expense, posting the outer boundaries of the filming activity, advance notice to affected property owners, businesses and tenants, and cleanup and restoration of public streets. The permittee must follow instructions from the police and fire department officers assigned to the site (Section 5.44.130 E). Every permit exemption in Section 5.44.040 disappears when a public street is closed.

Violations & Fines

Filming that closes a street without a permit violates Section 5.44.030 A, and Chapter 5.44 prints no penalty of its own, so Section 1.20.010 applies: a misdemeanor punishable by a fine of not more than one thousand dollars or imprisonment not to exceed six months, or both, unless made an infraction. The film development office can revoke a permit for breach of the permittee duties in Section 5.44.130, and a police officer can suspend it for an immediate hazard.

Frequently Asked Questions

How far ahead must I apply to close a street for filming in Pismo Beach?
Section 5.44.050 A requires applications that include street closures, major stunts or pyrotechnics to be filed with the film development office a minimum of thirty (30) days before the first day of filming. Other film permit applications need only fourteen (14) days. Late applications are not processed absent special circumstances or good cause.
Who approves a street closure for a film shoot?
The applicant requests the closure on the film permit application under Section 5.44.140. A short-term encroachment permit is then granted by the city administrator, his designee or the chief of police. The film development office decides the permit itself, normally within two business days of receiving the application.
Why would the city deny a filming permit involving a street?
Section 5.44.070 A allows denial where filming will substantially disrupt a public right-of-way or street when it is usually congested, interfere with emergency vehicles, or substantially interfere with street maintenance work or an authorized excavation permit. If reasonable conditions can correct the problem, the office can impose them instead of denying.

Sources & Official References

Other rules in Pismo Beach

All Pismo Beach rules

California rules heatmap·Compare Pismo Beach to another location·View the California filming & production overview

Get notified when Street Closures in Pismo Beach, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.