Pismo Beach, CA Parking Rules: EV Charging (2026)

Light Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Reviewer
The building official, administrative and nondiscretionary
Design standard
Article 625 of the California Electrical Code
Guidance document
Plug-In Electric Vehicle Infrastructure Permitting Checklist
Submittal
Email, internet or facsimile, with electronic signatures accepted
Use permit trigger
Specific, adverse impact on public health and safety, shown by substantial evidence
Association approval
Cannot be the basis or a condition of approval

Summary

In the City of Pismo Beach, California, Municipal Code § 15.12.020 sets an administrative, nondiscretionary expedited permit process for electric vehicle charging stations, run by the building official, with electronic submittal, standard plans and checklists, and safety standards drawn from the California Electrical Code.

B. Electric Vehicle Charging Station Requirements. 1. All electric vehicle charging stations shall meet applicable health and safety standards and requirements imposed by the state and the city. ... ... 1. The building official shall establish an administrative, nondiscretionary expedited permit application review process for electric vehicle charging stations, including standard plans and checklists. ... ... 4. An application for an electric vehicle charging station shall be administratively reviewed and approved by the building official as a nondiscretionary permit within in a reasonable time following receipt of a complete application that satisfies the requirements of the approved checklists and standard plans, and includes payment of all required permit processing and inspection fees. 5. The building official may require the applicant to apply for a use permit pursuant to other City Municipal Code provisions if the building official, based on substantial evidence, determines that the proposed electric vehicle charging station could have a specific, adverse impact upon the public health and safety.

Full Breakdown

Section 15.12.020 defines an electric vehicle charging station as any level of electric vehicle supply equipment station designed and built in compliance with Article 625 of the California Electrical Code that delivers electricity from a source outside an electric vehicle into a plug-in electric vehicle. Every station must meet the applicable health and safety standards and requirements imposed by the state and the city, plus the safety and performance standards of the California Electrical Code, the Society of Automotive Engineers, the National Electrical Manufacturers Association, accredited testing laboratories and, where applicable, the Public Utilities Commission on safety and reliability.

The building official must establish the expedited review process with standard plans and checklists that list every requirement a station must meet to qualify. The process must substantially conform to the "Plug-In Electric Vehicle Infrastructure Permitting Checklist" of the "Zero-Emission Vehicles in California: Community Readiness Guidebook" published by the Governor's Office of Planning and Research, though the building official can modify the checklists for unique climactic, geological, seismological or topographical conditions. Checklists, standard plans and other required documents are posted on the City of Pismo Beach website.

An applicant can file by email, internet or facsimile, pay the permit processing and inspection fees as specified on the city website, and sign electronically. The application is complete when it satisfies the information requirements in the checklists and standard plans. If it is incomplete, a written correction notice detailing all deficiencies is sent for resubmission. A complete application is approved administratively as a nondiscretionary permit within a reasonable time. The building official can require a use permit under other Municipal Code provisions if, based on substantial evidence, the station could have a specific, adverse impact upon public health and safety, defined as a significant, quantifiable, direct and unavoidable impact based on objective, written standards as they existed on the date the application was deemed complete. Approval shall not be based or conditioned on the approval of an association as defined in Section 4080 of the Civil Code.

Violations & Fines

Section 15.12.020 prints no penalty clause of its own. Chapter 1.20 supplies the penalty. Under § 1.20.010 a violation of a city ordinance is a misdemeanor unless made an infraction, punishable by a fine of not more than one thousand dollars, imprisonment not to exceed six months, or both. Infraction fines are not exceeding one hundred dollars, two hundred dollars and five hundred dollars for a first, second and third or later violation within twelve months, and each day is a separate offense.

Frequently Asked Questions

Does a charging station need a permit in the City of Pismo Beach?
Section 15.12.020 sets up a permit application process for electric vehicle charging stations, reviewed by the building official on standard plans and checklists. An application is approved as a nondiscretionary permit within a reasonable time once it is complete and the permit processing and inspection fees are included.
What standards must a Pismo Beach charging station meet?
Section 15.12.020(B) requires applicable state and city health and safety standards, plus the safety and performance standards of the California Electrical Code, the Society of Automotive Engineers, the National Electrical Manufacturers Association, accredited testing laboratories and, where applicable, the Public Utilities Commission. The definition also ties the station to Article 625 of the California Electrical Code.
Can I apply for a charging station permit electronically?
Yes. Section 15.12.020(D) allows email, internet or facsimile submittal, including payment of permit processing and inspection fees as specified on the City of Pismo Beach website, and it accepts electronic signatures in place of a wet signature. Checklists and standard plans are posted on the same website.
Can my homeowners association block a charging station permit in Pismo Beach?
Section 15.12.020(D)(6) says approval of a charging station permit application shall not be based or conditioned on the approval of an association as defined in Section 4080 of the Civil Code. The building official reviews the application against the checklist requirements and any specific, adverse impact finding.

Sources & Official References

Other rules in Pismo Beach

All Pismo Beach rules

California rules heatmap·Compare Pismo Beach to another location·View the California parking rules overview

Get notified when EV Charging in Pismo Beach, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.