Key Facts

Minimum elevation
12 inches above road crown
Survey deadline
20 days after slab poured
Enforcement tool
Building official's Stop Work Order
Adopted by
Ord. No. 16-203 (2016), amended 2022

Summary

Every new structure in Daytona Beach must set its finished floor at least 12 inches above the crown of the adjacent road, a citywide standard under LDC Section 6.23 that applies on top of, and yields to, any stricter Florida Building Code flood elevation requirement.

A minimum finished floor elevation height of 12 inches above the crown of the road adjacent to the front of the lot or parcel shall be required unless the City's engineering division approves other elevations. In case of conflict between the foregoing elevation requirement and any elevation requirements contained in the Florida Building Code, the more stringent requirement shall apply. In determining the minimum finished floor elevation relative to crown of the road, the applicant shall evaluate existing stormwater topography and establish the minimum finished floor elevation sufficient to protect the structure from flooding. A signed and sealed as-built survey of the finished floor elevation must be submitted to the City's permitting authority within 20 days after the slab has been poured. The building official shall be authorized to issue a stop work order if the as-built survey is not submitted within the time required.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 78 | Land Development Code: Supplement 36).

Full Breakdown

23 sets a baseline elevation rule that applies regardless of flood zone: the finished floor of a new structure must sit at least 12 inches above the crown of the road fronting the lot, unless the City's engineering division approves a different elevation. Where this 12-inch rule conflicts with a Florida Building Code flood elevation requirement, such as the base-flood-elevation-plus-1-foot freeboard that applies in flood hazard areas, the more stringent of the two controls. Before settling on a finished floor height, the applicant must evaluate the site's existing stormwater topography and set the elevation high enough to protect the structure from flooding, not simply meet the 12-inch minimum.

Compliance is checked on the back end: a signed and sealed as-built survey documenting the actual finished floor elevation must reach the City's permitting authority within 20 days after the slab is poured. If that survey does not arrive on time, the building official is authorized to issue a Stop Work Order, halting further construction until the elevation is verified. The rule was adopted by Ordinance No. 16-203 in 2016 and amended by Ordinance No. 2022-238 in 2022.

Violations & Fines

Missing the 20-day deadline to file the as-built finished-floor survey after the slab is poured triggers a Stop Work Order from the building official, stopping all further construction until an accurate survey is on file. Building below the required 12-inch elevation without engineering division approval is a Land Development Code violation subject to Article 10's civil citations and correction orders.

Frequently Asked Questions

How high must a new house's floor be above the street in Daytona Beach?
At least 12 inches above the crown of the road fronting the lot, per LDC Section 6.23, unless the City's engineering division signs off on a different elevation based on site stormwater conditions.
What happens if I don't submit the finished-floor survey on time?
The building official can issue a Stop Work Order. LDC Section 6.23 gives you 20 days after the slab is poured to submit a signed and sealed as-built survey of the finished floor elevation to the City's permitting authority.
Does the Florida Building Code override the City's 12-inch rule?
Only if it is stricter. Section 6.23 states that where the City's 12-inch-above-crown rule conflicts with a Florida Building Code elevation requirement, whichever standard is more stringent applies to the project.

Sources & Official References

Other rules in Daytona Beach

All Daytona Beach rules

Florida rules heatmap·Compare Daytona Beach to another location·View the Florida hurricane preparedness overview

Get notified when Flood Elevation in Daytona Beach, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.