Key Facts

Zone AE outside HSDRRS
BFE + 2 ft freeboard
Zone AE inside HSDRRS
highest of BFE+1ft, 18in above street, or -3.5 NAVD88
Zone VE
BFE + 1 ft, breakaway walls required
Enclosed area limit below BFE
299 sq ft
Certification required from
PE, architect, or land surveyor

Summary

New residential construction in Jefferson Parish's mapped flood zones must sit above a set NAVD 88 elevation, noted right on the building permit. Outside the parish's Hurricane Storm Damage Risk Reduction System, Zone AE homes must have their lowest floor at the base flood elevation plus two feet of freeboard, with any enclosed space below that line capped at 299 square feet.

These county ordinances apply to unincorporated areas of Jefferson Parish. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Permits issued for new construction of any residential structure, must have the required NAVD 88 elevation of the lowest floor or lowest horizontal portion of the structural member and the base flood elevation noted on the permit. ... (3)In Zone AE outside the Hurricane Storm Damage Risk Reduction System (HSDRRS), the lowest floor shall be at:a.The BFE on the FIRM plus two (2) feet of freeboard; andb.The total floor area of any new enclosed area below the BFE shall not exceed two hundred ninety-nine (299) square feet, including breakaway walls.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 20 Update 2).

Full Breakdown

Sec. 1 sets four elevation tiers depending on flood zone and whether the lot sits inside the parish's Hurricane Storm Damage Risk Reduction System (HSDRRS). 5 NAVD 88. Outside the HSDRRS, Zone AE steps up to BFE plus two feet of freeboard, reflecting the added risk away from the levee system. In Zone VE, the coastal high-hazard zone, the bottom of the lowest horizontal structural member must sit at BFE plus one foot, fill cannot be used for structural support, and the space below must stay open or be built with breakaway walls.

"Lowest floor" under this chapter includes the basement, mechanical and utility equipment, and ductwork, and a registered professional engineer, architect, or land surveyor must certify to the Department of Building Permits that the elevation meets this chapter, the Louisiana State Uniform Construction Code, and the parish's building code. Manufactured homes and recreational vehicles placed in these zones must separately meet the anchoring and elevation standards of Sec. 5 and Sec. 6.

Violations & Fines

Elevation violations are enforced by the Department of Building Permits under Sec. 14-7.4, which ties to the Code's general penalty, Sec. 1-10: up to $1,000.00 and up to six months imprisonment, with each day of noncompliance a separate offense. Where a crawlspace under a home outside the HSDRRS exceeds five feet, Sec. 14-6.1(6) also requires recording a declaration of land use restriction with the Clerk of Court before a permit issues, and the floodplain administrator may inspect for illegal conversion annually with 72-hour notice.

Frequently Asked Questions

How much freeboard does Jefferson Parish require above base flood elevation?
It depends on the zone and whether you're inside the Hurricane Storm Damage Risk Reduction System. Zone AE outside the HSDRRS requires the lowest floor at BFE plus two feet of freeboard under Sec. 14-6.2.1(3); Zone AE inside the HSDRRS and Zone VE both use one foot of freeboard instead.
What is NAVD 88 and why does it matter?
NAVD 88 is the North American Vertical Datum of 1988, the elevation reference the parish uses for base flood elevations on FEMA's Flood Insurance Rate Maps. Sec. 14-6.2.1 requires your permit to list your lowest floor's actual NAVD 88 elevation so inspectors can confirm compliance before a completion certificate issues.
Can I finish out the space under my elevated house?
No. Sec. 14-6.2.1(3)(b) and (4)(b) cap any new enclosed area below the base flood elevation at 299 square feet, including breakaway walls, and Sec. 14-6.1(6) requires a recorded declaration of land use restriction limiting that space to storage, parking, or access when the crawlspace exceeds five feet.
Who has to certify my home meets these elevation standards?
Sec. 14-6.2 requires a registered professional engineer, architect, or land surveyor to certify to the Department of Building Permits that your structure satisfies this chapter, the Louisiana State Uniform Construction Code, and the parish's building code before you get a completion certificate.

Sources & Official References

Other rules in Jefferson Parish

All Jefferson Parish rules

Compare Jefferson Parish to another location·View the Louisiana hurricane preparedness overview

Get notified when Flood Elevation in Jefferson Parish, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.