Marietta, GA Hurricane Preparedness: Flood Elevation (2026)
Key Facts
- Certificate required
- FEMA elevation certificate (or floodproofing certificate)
- When filed
- immediately after lowest floor/floodproofing completed
- Who certifies
- licensed land surveyor or professional engineer
- Noncompliance
- stop-work order; up to $1,000 fine/60 days jail
- Administering official
- Public Works Director
Summary
Marietta sits well inland in Cobb County, but its floodplain ordinance still requires builders to prove a structure meets the city's flood elevation standard before it can be used. City Code § 7-8-10-030(C) requires a certified FEMA elevation certificate showing the lowest floor elevation, filed with the public works director immediately after that floor is built.
C.Construction Stage Submittal Requirements. For all new construction and substantial improvements on sites with a floodplain management/flood damage prevention plan, the permit holder shall provide to the public works director or designee a certified as-built FEMA elevation certificate or floodproofing certificate for non-residential construction including the lowest floor elevation or floodproofing level immediately after the lowest floor or floodproofing is completed. ... Any work undertaken prior to approval of these certifications shall be at the permit holder's risk. ... Failure to submit certification or failure to make the corrections required hereby shall be cause to issue a stop-work order for the project.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 56).
Full Breakdown
Because Marietta's flood risk comes from Chattahoochee River tributaries and heavy rain events, including remnants of Gulf tropical systems, rather than coastal storm surge, the city's readiness tool is a paperwork checkpoint rather than an evacuation zone: the elevation certificate. Section 7-8-10-030(C) requires, for all new construction and substantial improvements on a site covered by an approved floodplain management plan, a certified as-built FEMA elevation certificate showing the lowest floor elevation, filed right after that floor is completed. A licensed land surveyor or professional engineer must prepare and certify it.
Non-residential buildings that chose floodproofing instead of elevation submit a FEMA floodproofing certificate prepared by a licensed engineer or architect, along with a design and operation and maintenance plan showing how the floodproofing measures will keep working over time. The public works director reviews the submission for deficiencies, and any defect found must be corrected immediately, before further construction proceeds. Anyone who builds past the lowest-floor stage before the certificate is approved does so, in the code's words, "at the permit holder's risk," meaning later corrections to meet the three-foot freeboard standard in § 7-8-10-050 come out of the owner's pocket regardless of how much has already been built.
Violations & Fines
Failing to submit the required elevation or floodproofing certificate, or failing to make corrections the public works director identifies, is cause under § 7-8-10-030(C) to issue a stop-work order halting the project. Continued or flagrant noncompliance escalates to the article's general enforcement provisions at § 7-8-10-070, including withheld certificates of occupancy and municipal court penalties of up to $1,000.00 and/or 60 days' imprisonment per day of violation.
Frequently Asked Questions
Does Marietta require flood elevation certificates even though it isn't coastal?
Who can sign Marietta's flood elevation certificate?
What if I build before submitting the certificate?
Sources & Official References
Other rules in Marietta
Compare Marietta to another location·View the Georgia hurricane preparedness overview
See something wrong?