Key Facts

Residential rule
Elevate to regulatory flood protection elevation, Sec. 9-52(1)
Nonresidential alternative
Floodproof to same elevation, Sec. 9-52(2)
Manufactured home chassis
Engineered foundation over 36 inches high
Evacuation plan
Required for manufactured home parks, Sec. 9-52(3)(d)
Temporary structure removal
72 hours before hurricane landfall, Sec. 9-52(7)

Summary

Rowan County requires every new or substantially improved building in a mapped flood hazard area to sit at or above the regulatory flood protection elevation, the standard the county also relies on for hurricane and storm-surge risk. Residential structures must be elevated; commercial buildings can be elevated or floodproofed to the same level.

These county ordinances apply to unincorporated areas of Rowan County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(1)Residential construction. New construction and substantial improvement of any residential structure (including manufactured homes) shall have the reference level, including basement, elevated no lower than the regulatory flood protection elevation, as defined in section 9-5 of this chapter.(2)Nonresidential construction. New construction and substantial improvement of any commercial, industrial, or other nonresidential structure shall have the reference level, including basement, elevated no lower than the regulatory flood protection elevation, as defined in section 9-5 of this chapter. Structures located in A or AE zones may be floodproofed to the regulatory flood protection elevation in lieu of elevation provided that all areas of the structure, together with attendant utility and sanitary facilities, below the regulatory flood protection elevation are watertight with walls substantially impermeable to the passage of water, using structural components having the capability of resisting hydrostatic and hydrodynamic loads and the effect of buoyancy.

Full Breakdown

Sec. 9-52 of the Rowan County Code sets the specific construction standards that apply once a base flood elevation has been established under Sec. 9-7 or Sec. 9-54. Subsection (1) requires new construction and substantial improvement of any residential structure, including manufactured homes, to have the reference level, including basement, elevated no lower than the regulatory flood protection elevation defined in Sec. 9-5. Subsection (2) applies a parallel rule to nonresidential buildings but allows floodproofing as an alternative: structures in zones A or AE may be floodproofed to the regulatory flood protection elevation instead of elevated, provided the space below that elevation is watertight, using components able to resist hydrostatic and hydrodynamic loads and buoyancy.

Manufactured homes get a further rule under Sec. 9-52(3): the chassis must be supported by reinforced piers or an engineered foundation, and if the chassis sits more than thirty-six inches above grade, an engineering certification is required. These construction elevation rules sit alongside the county's hurricane and storm evacuation planning: Sec. 9-52(3)(d) requires an evacuation plan, filed with and approved by the floodplain administrator and the local emergency management coordinator, for any new or substantially improved manufactured home park in a flood-prone area. Sec. 9-52(7) separately requires a removal plan for temporary nonresidential structures in the floodplain, specifying removal at least seventy-two hours before a hurricane makes landfall or immediately upon a flood warning.

Violations & Fines

Building below the regulatory flood protection elevation without a variance is a Class 1 misdemeanor under Sec. 9-13, fined up to fifty dollars and up to thirty days imprisonment, with each day of noncompliance a separate offense. A variance granted to build below base flood elevation still requires written notice, under Sec. 9-35(7), that flood insurance premiums can rise by up to twenty-five dollars per hundred dollars of coverage. The floodplain administrator can order a stop-work under Sec. 9-33(16) or withhold a certificate of occupancy until the elevation certificate is corrected.

Frequently Asked Questions

How high must I build in a Rowan County flood zone before a hurricane?
Sec. 9-52(1) requires new or substantially improved residential structures, including manufactured homes, to have their reference level elevated no lower than the regulatory flood protection elevation defined in Sec. 9-5, which is base flood elevation plus two feet of freeboard. Nonresidential buildings can meet the same elevation through floodproofing under Sec. 9-52(2).
Does Rowan County require a hurricane evacuation plan for manufactured home parks?
Yes. Sec. 9-52(3)(d) requires an evacuation plan for all residents of any new, substantially improved, or substantially damaged manufactured home park or subdivision in a flood-prone area, filed with and approved by both the floodplain administrator and the local emergency management coordinator.
Can I keep a temporary structure in the floodplain during hurricane season?
Only with an approved removal plan. Sec. 9-52(7) limits temporary nonresidential structures in the floodplain to a permitted period of up to three months, renewable to one year, and requires the applicant to remove the structure at least seventy-two hours before a hurricane's landfall or immediately upon a flood warning.

Sources & Official References

Other rules in Rowan County

All Rowan County rules

Compare Rowan County to another location·View the North Carolina hurricane preparedness overview

Get notified when Flood Elevation in Rowan County, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.