Sampson County, NC Hurricane Preparedness: Flood Elevation (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Form required
FEMA Form 086-0-33 Elevation Certificate
Pre-construction cert
Due before any new construction starts
Final cert
Required before Certificate of Compliance/Occupancy issuance
Photo requirement
At least 2 color photos, minimum 3 by 3 inches
Variance warning
Premiums may rise up to $25 per $100 of coverage

Summary

Before breaking ground on new construction in a Sampson County Special Flood Hazard Area, the permit holder must give the Floodplain Administrator a FEMA Elevation Certificate proving the reference level's height. Sec. 2-3-04.B(3)(a) requires it before and after construction, and Sec. 2-3-04.E(7) makes the county warn variance recipients that building below the Base Flood Elevation raises flood-insurance costs.

These county ordinances apply to unincorporated areas of Sampson County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(i) An Elevation Certificate (FEMA Form 086-0-33) is required prior to the actual start of any new construction. It shall be the duty of the permit holder to submit to the Floodplain Administrator a certification of the elevation of the reference level, in relation to NAVD 1988. The Floodplain Administrator shall review the certificate data submitted. Deficiencies detected by such review shall be corrected by the permit holder prior to the beginning of construction. Failure to submit the certification or failure to make required corrections shall be cause to deny a floodplain development permit. ... Any applicant to whom a variance is granted shall be given written notice specifying the difference between the BFE and the elevation to which the structure is to be built and that such construction below the BFE increases risks to life and property, and that the issuance of a variance to construct a structure below the BFE may result in increased premium rates for flood insurance up to $25 per $100 of insurance coverage.

Full Breakdown

Sec. 2-3-04.B(3)(a)(i) requires an Elevation Certificate (FEMA Form 086-0-33) before a permit holder starts any new construction in a Special Flood Hazard Area, certifying the reference level's elevation relative to NAVD 1988; the Floodplain Administrator reviews it and can deny the Floodplain Development Permit if deficiencies are not corrected first. A second, Finished Construction Elevation Certificate is due after construction and before the county issues a Certificate of Compliance/Occupancy, and it must include at least two color photographs of the building's front and rear, at least 3 inches by 3 inches, taken within 90 days of certification, plus extra side-view shots for split-level homes and a foundation photo showing any flood openings.

This paperwork matters most going into hurricane season: property owners who cannot show a compliant elevation certificate risk having their permit or occupancy held up right when storm-driven flooding is most likely. Separately, Sec. 2-3-04.E(7) requires that anyone granted a variance to build below the Base Flood Elevation receive written notice of the exact gap between the BFE and the approved build elevation, along with a warning that building below the BFE increases risk to life and property and can raise flood insurance premiums by as much as $25 per $100 of coverage.

Violations & Fines

Missing or deficient elevation paperwork carries its own consequence separate from the ordinance's Class 1 misdemeanor: the Floodplain Administrator must deny the Floodplain Development Permit if the pre-construction Elevation Certificate is not submitted or corrected, and must withhold the Certificate of Compliance/Occupancy if the Finished Construction Elevation Certificate is missing or shows the building was built below the required elevation, per Sec. 2-3-04.B(3)(a).

Frequently Asked Questions

What Elevation Certificate does Sampson County require before construction?
FEMA Form 086-0-33, certifying the reference level's elevation relative to NAVD 1988, submitted to the Floodplain Administrator before any new construction begins in a Special Flood Hazard Area, under Sec. 2-3-04.B(3)(a)(i).
What happens if I skip the pre-construction elevation certificate?
The Floodplain Administrator must deny the Floodplain Development Permit until the certificate is submitted and any deficiencies are corrected, since Sec. 2-3-04.B(3)(a)(i) makes the certification a condition of construction beginning.
What does the final elevation certificate need to include?
A Finished Construction Elevation Certificate with at least two color photographs of the building's front and rear, each at least 3 inches by 3 inches and taken within 90 days, plus side-view and foundation photos when applicable, per Sec. 2-3-04.B(3)(a)(ii).
What if my Sampson County variance lets me build below the Base Flood Elevation?
Sec. 2-3-04.E(7) requires written notice of the exact gap between the BFE and your build elevation and a warning that building below the BFE can raise flood insurance premiums by up to $25 per $100 of coverage.

Sources & Official References

Other rules in Sampson County

All Sampson County rules

Compare Sampson County to another location·View the North Carolina hurricane preparedness overview

Get notified when Flood Elevation in Sampson County, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.