Key Facts
- Code section
- AVMC 7.30.030(C)
- Chapter applies since
- December 1, 2015
- New construction trigger
- 500 square feet or more of aggregate landscaped area
- Rehabilitated trigger
- 2,500 square feet or more of aggregate landscape area
- Rainwater track
- Under 2,500 square feet of landscape, water need met entirely on site
- Standard that applies
- Appendix D, Section 5 of the State Model WELO
- Enforcer
- City manager
Summary
In the City of Aliso Viejo, California, rainwater capture appears in the water efficient landscape chapter at AVMC 7.30.030(C). A lot with under 2,500 square feet of landscaped area that meets its entire landscape water requirement with stored rainwater capture on site, or with graywater, is subject only to Appendix D, Section 5 of the State Model Water Efficient Landscape Ordinance.
A. Beginning December 1, 2015, this chapter shall apply to the following: 1. All new construction projects with an aggregate landscaped area equal to or greater than 500 square feet that require a building or landscape permit, plan check, or design review; 2. All rehabilitated landscape projects with an aggregate landscape area equal to or greater than 2,500 square feet that require a building or landscape permit, plan check, or design review. ... C. New construction or rehabilitated landscape projects that use treated or untreated graywater or rainwater capture on site, any lot or parcel within the project that has less than 2,500 square feet of landscaped area and meets the lot or parcel’s landscape water requirement (estimated total water use) entirely with treated or untreated graywater or through stored rainwater capture on site is subject only to Appendix D, Section 5 of the State Model Water Efficient Landscape Ordinance.
Full Breakdown
Section 7.30.030 sets who must follow Chapter 7.30. Beginning December 1, 2015, the chapter applies to new construction projects with an aggregate landscaped area of 500 square feet or more that require a building or landscape permit, plan check or design review, and to rehabilitated landscape projects with an aggregate landscape area of 2,500 square feet or more that require the same.
Rainwater capture enters in subsection C. For a new construction or rehabilitated landscape project that uses treated or untreated graywater or rainwater capture on site, any lot or parcel in the project with less than 2,500 square feet of landscaped area that meets its landscape water requirement (estimated total water use) entirely with graywater or stored rainwater capture is subject only to Appendix D, Section 5 of the State Model Water Efficient Landscape Ordinance. It is the only provision in the Aliso Viejo code that uses the term rainwater, so it works as a compliance path inside the landscape rules, not as a stand-alone permit program.
Subsection D separately lets any landscape project of 2,500 square feet or less comply by following Appendix D of the state model ordinance. Subsection E excludes registered local, state or federal historical sites, ecological restoration and mined-land reclamation projects that do not need a permanent irrigation system, existing plant collections at botanical gardens and arboretums open to the public, and cemeteries, with limited exceptions for cemetery projects.
Projects that are covered still file a landscape submittal sheet and landscape documentation package before installation (7.30.040). A licensed landscape professional certifies the design and water use calculations, and compliance is verified through a certificate of completion tied to the certificate of use and occupancy or the permit final. The city's findings in section 7.30.020 record that average rainfall in Orange County is approximately 12 inches per year. The city manager administers and enforces the chapter (7.30.060).
Violations & Fines
The city manager and authorized enforcement officers enforce Chapter 7.30 (7.30.060). The city can bring a civil action for an injunction and recover investigation and legal costs (7.30.070). An invoice for costs is immediately due and can include reasonable attorneys' fees, and the council can fix other penalties and fees by resolution (7.30.080). Chapter 1.06 penalties also apply, including a misdemeanor fine of not more than $1,000 or up to six months in jail.
Frequently Asked Questions
Does Aliso Viejo recognize rainwater capture for landscape water needs?
Which landscape projects have to follow Chapter 7.30?
What about a small landscape of 2,500 square feet or less?
Who enforces the landscape water rules and what can the city recover?
Sources & Official References
Other rules in Aliso Viejo
California rules heatmap·Compare Aliso Viejo to another location·View the California landscaping rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Rainwater Harvesting in Nearby Cities
How other cities in Orange County handle rainwater harvesting.