South Bend, IN Landscaping Rules: Tree Trimming (2026)
Key Facts
- Required clearance
- 10 feet above the curb
- Minimum notice period
- 10 days
- Who trims
- Board of Park Commissioners or owner on order
- Also can't obstruct
- Streetlights, signs, signals, intersections
- Non-compliance remedy
- City trims, assesses cost as a lien
Summary
Trees and shrubs overhanging a South Bend street, whether in the tree lawn or on an abutting lot, must be trimmed to keep 10 feet of clearance above the curb. The Board of Park Commissioners or the property owner, on the Board's order, does the trimming within at least 10 days of notice.
(a)All trees and shrubs which overhang a street within the City, whether located on tree and lawn areas or on the abutting lots, shall be trimmed either by the Board of Park Commissioners or by the owners of the abutting lots upon the order of the Board.(b)The trimming shall be done within the period specified in the notice given by the Board to the owners, as provided in section 19-21; provided, however, such period shall not be less than ten (10) days.(c)Overhanging trees shall be trimmed so that there is a clear space of ten (10) feet above the surface of the curb and in such a manner as not to obstruct the view of any streetlight, traffic sign, signal device or street intersection.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 65).
Full Breakdown
Sec. 19-18 requires all trees and shrubs overhanging a City street, whether they sit in the public tree and lawn area or on an abutting private lot, to be trimmed either by the Board of Park Commissioners directly or by the abutting owner acting on the Board's order. The trimming must happen within the period stated in the Board's written notice, and that period can never be shorter than ten days. The trim itself has a specific standard: overhanging branches must be cut back so there is a clear space of ten feet above the curb surface, and the trimming must be done in a way that does not obstruct the view of any streetlight, traffic sign, signal device or street intersection.
This sits alongside the Sec. 19-17 planting standards for the same tree and lawn areas, which require the lowest limbs of newly planted trees to start at least ten feet above the curb and sidewalk in the first place, so the ten-foot clearance is the baseline the City maintains over the life of the tree. Notice for a trim order is served the same way as other Article 1 notices under Sec. 19-21: personally or by leaving a copy at the owner's residence if they live in the City, by registered mail if they live elsewhere, or by newspaper publication for two consecutive weeks if the owner cannot be located.
If the owner fails to trim as ordered, the Board can do the work itself under Sec. 19-20 and assess the cost as a lien on the property.
Violations & Fines
Failing to trim an overhanging tree as ordered by the Board of Park Commissioners within the notice period, never less than ten days, is a violation of Article 1 subject to the penalty in Sec. 1-23 under Sec. 19-23, in addition to liability for the City's cost of performing the trim itself, which becomes a lien on the property under Sec. 19-20.
Frequently Asked Questions
How much clearance must overhanging trees keep above a South Bend street?
Who is responsible for trimming a tree that overhangs a South Bend street?
What happens if I don't trim my overhanging tree after South Bend orders it?
Sources & Official References
Other rules in South Bend