Skip to main content
CityRuleLookup

Jacksonville, FL Noise Ordinances: Construction Hours (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Construction hours in Jacksonville, FL, sometimes called construction noise rules or contractor work-hour ordinances, set when contractors can run power tools, hammers, and heavy equipment.

Key Facts

Curfew hours
10:00 p.m. to 7:00 a.m.
Overnight equipment exception
generators, mudhogs, well point pumps only
Exception noise cap
60 dBA maximum
Civil penalty
$250 per minor violation
Continuing violation
each day is a separate offense
Enforced by
Environmental Protection Board Department staff

Summary

Jacksonville's noise ordinance bars construction work between 10:00 p.m. and 7:00 a.m. under Ordinance Code Sec. 360.701(a)(29). Generators, mudhogs, and well point pumps may keep running overnight, but only if they stay at or under 60 dBA. The Environmental Protection Board's Department can ticket violators directly, without a full court case, and each violation carries a $250 civil penalty.

(29)Allowing or performing construction between 10:00 p.m. and 7:00 a.m., in violation of the Board's rules with respect to noise pollution control. However, generators, mudhogs, and well point pumps may be operated during this time period, but sound emitted from the operation of this equipment shall not exceed 60 dBA, in violation of the Board's rules with respect to noise pollution control. ... (b)Each such minor violation shall be subject to a civil penalty of $250.(c)Each day during any part of which an offense, specified in subsection (a) occurs shall constitute a separate offense.

Source: Jacksonville Environmental Quality DivisionView official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 6 Update 1).

Full Breakdown

Sec. 701 lets the Jacksonville Environmental Protection Board, acting through its Department staff, write citations for a defined list of 'minor violations' instead of pursuing a full enforcement case under Chapter 360's Part 4. , in violation of the Board's noise pollution control rules. The section carves out one exception: generators, mudhogs, and well point pumps can keep running through the curfew, but only if the sound they produce does not exceed 60 dBA. Anyone running louder equipment during those hours, or doing any other construction work at all in that window, is ticketable.

Because this is a minor-violation track, the Department issues the citation directly rather than building a full case the way a Part 4 nuisance action would require. for a full week can rack up seven separate $250 citations. Builders working late on foundation pours, generator-powered lighting rigs, or well-point dewatering systems for a construction site need to plan around the curfew or keep their equipment at or under the 60 dBA cap to avoid a citation.

Violations & Fines

Violating the construction-hours curfew is a $250 civil penalty per Sec. 360.701(b), and each day the violation continues is a separate offense under Sec. 360.701(c), so a job site caught running loud equipment past 10:00 p.m. for a week can face $1,750 in citations. The Environmental Protection Board's Department staff issues the ticket directly under its minor-violation authority, supplementing the Board's full Chapter 360 enforcement powers.

Frequently Asked Questions

What hours is construction noise banned in Jacksonville?
Construction work is barred between 10:00 p.m. and 7:00 a.m. under Sec. 360.701(a)(29) of the Ordinance Code, enforced by the Environmental Protection Board's Department staff as a minor violation. The only carve-out is for generators, mudhogs, and well point pumps, which may run overnight as long as they stay at or under 60 dBA.
What's the fine for construction noise after 10 p.m. in Jacksonville?
Each minor violation carries a flat $250 civil penalty under Sec. 360.701(b), issued directly by the Environmental Protection Board's Department staff. Sec. 360.701(c) makes every day the violation continues a separate offense, so repeated overnight work stacks additional $250 citations day by day.
Can generators run overnight on a Jacksonville job site?
Yes, but only generators, mudhogs, and well point pumps get the overnight exception, and only if their sound output does not exceed 60 dBA. Any other equipment, or these three types running louder than 60 dBA, is a ticketable minor violation between 10:00 p.m. and 7:00 a.m.

Sources & Official References

Other rules in Jacksonville

All Jacksonville rules

How Jacksonville compares: Cities with the Strictest Construction Hours·Florida rules heatmap·Compare Jacksonville to another location·View the Florida noise ordinances overview

Get notified when Construction Hours in Jacksonville, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.