Lewis County, WA Parking Rules: EV Charging (2026)
Key Facts
- EV charging standard
- WAC 51-50-0429 (state code)
- Applies when
- Development requires off-street parking
- Location
- Packwood and Onalaska Small Town UGAs
- Parking ban
- No parking in Hwy 12/SR 508 setback
- Legacy parking
- Vested if built before Jan. 1, 2026
Summary
New development in Lewis County's Packwood and Onalaska Small Town Urban Growth Areas that must provide off-street parking also has to provide electric vehicle charging space, built to the state's standard in WAC 51-50-0429, as part of the zone's overall vehicle parking chapter.
(1) Purpose. ... The purpose of this section is to ensure that new development provides a minimum number of off-street parking spaces to reduce congestion on public rights-of-way. ... (i) Electrical vehicle charging space shall be provided in accordance with WAC 51-50-0429.
Full Breakdown
220 is the vehicle parking chapter for Lewis County's Small Town Urban Growth Areas at Packwood and Onalaska. Its stated purpose is to make sure new development supplies enough off-street parking to keep congestion off Highway 12 and State Route 508, and subsection (3) lists the design standards every project with a parking requirement must meet, including stall counts from Table 4, dimensions from Table 5, and aisle widths from Table 6. Within that same list of standards, subsection (3)(i) requires that electrical vehicle charging space be provided in accordance with WAC 51-50-0429, the state building code's electric vehicle charging infrastructure standard, rather than setting its own local stall count or amperage requirement.
Because the requirement is folded into the general parking standards, it applies to the same commercial, industrial, multifamily and mixed-use projects that trigger Table 4's minimum parking counts, and it is reviewed alongside those counts at building permit and site plan stage. The chapter separately bars any new parking, including EV parking, from being sited within the front setback along Highway 12 or State Route 508, and it grandfathers parking that existed before January 1, 2026, while barring that legacy parking from being expanded in a way that increases its nonconformity.
05 LCC, which adopts the state building and electrical codes referenced in WAC 51-50-0429. The section was adopted by Ord. 1367 (Exh. C) in 2025.
Violations & Fines
Building a covered project without the WAC 51-50-0429 electric vehicle charging space required by LCC § 17.17.220(3)(i) is a civil infraction under LCC § 17.07.010, run through Chapter 1.20 LCC's enforcement process, with each day of noncompliance a separate offense, and the county can withhold a certificate of occupancy until the required charging infrastructure is installed.
Frequently Asked Questions
Does Lewis County require EV charging stations for new construction?
Does the county set its own EV charging stall count?
Can I put EV charging spaces in my front setback along Highway 12?
Sources & Official References
Other rules in Lewis County
Compare Lewis County to another location·View the Washington parking rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.