Fresno County, CA Parking Rules: EV Charging (2026)
Key Facts
- Governing chapter
- Fresno County Code Ch. 15.80
- Adopted
- Ord. No. 23-001, Feb. 28, 2023
- State mandate
- Gov't Code § 65850.7 / AB 1236
- Electrical standard
- Article 625, Calif. Electrical Code
- HOA approval
- Cannot be required as a condition
- Submittal method
- Online portal or email accepted
Summary
Fresno County must run an expedited, streamlined permitting process for electric vehicle charging stations under Chapter 15.80 of the County Code. The Building Official has to approve a complete application and cannot force an association's sign-off, though a specific safety finding can trigger a use permit instead.
A permit application that satisfies the information requirements in the adopted checklist shall be deemed complete and be promptly processed. Upon confirmation by the Building Official, or his/her designee, that the permit application and supporting documents meets the requirements of the, adopted checklist, and is consistent with all applicable laws, ordinances, and health and safety standards, the Building Official shall, consistent with Government Code Section 65850.7, approve the application and issue all necessary permits. Such approval does not authorize an applicant to energize or utilize the electric vehicle charging station until inspection approval is granted by the County of Fresno.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 51).
Full Breakdown
80 of the Fresno County Code, adopted by Ord. No. 7. 030 requires that a permit application meeting the county's adopted checklist, drawn from the "Plug-In Electric Vehicle Infrastructure Permitting Checklist," be deemed complete and promptly processed; the Building Official or a designee must then approve it and issue all necessary permits. Applicants cannot energize or use the station until Fresno County has completed a final inspection. If the application is incomplete, the Building Official issues a written correction notice detailing every deficiency. 030(C) allows electronic submittal, including through the county's online Customer Portal or by email, and accepts electronic signatures in place of a wet signature.
040 lets the Building Official require a use permit if there is substantial evidence of a specific, adverse impact on public health or safety, but bars conditioning approval on sign-off from a homeowners' association under Civil Code Section 4080. 050 requires charging equipment and its wiring, bonding, disconnecting means, and overcurrent protection to meet Article 625 of the California Electrical Code, and requires the load to be treated as continuous for electrical load calculations. 060 makes this chapter control over any less restrictive conflicting local law.
Violations & Fines
Installing or energizing a charging station without the required county permit and final inspection is a code violation enforceable by the Building Official, who may also require corrective permitting. An unpermitted station discovered during inspection can be ordered brought into compliance with Article 625 of the California Electrical Code before it may be energized or used.
Frequently Asked Questions
Does Fresno County require a permit for a home EV charger?
Can my homeowners association block my EV charger permit?
Can I submit my EV charger permit application online?
Sources & Official References
Other rules in Fresno County