Pacifica, CA Sidewalk & Pedestrian Rules: Encroachment Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit issuer
Community and Economic Development Director
Lead time to secure permit
2 working days before work
Moratorium on new pavement
3 years after paving
Extra fee
Utility Pavement Cut Recovery Fee
Permit status
Nontransferable

Summary

No one may occupy, open, tear up, or excavate any street, sidewalk, parking strip or public easement in the City of Pacifica without an encroachment permit from the Community and Economic Development Director. Permits must be secured at least two working days before work starts, and excavators also owe a Utility Pavement Cut Recovery Fee before the City will issue the permit.

No person shall occupy, open, tear up, break out, or excavate in any roadway, street, thoroughfare, sidewalk, parking strip, or public easement for the purpose of the installation, maintenance, or repair of underground facilities, or for any other purpose, without having obtained a permit therefor as required by the provisions of this article. ... The p ... ermits required by the provisions of this article shall be ... secured at least two (2) working days before the work is commenced, except in the event of emergencies. ... No person shall excavate in a public right-of-way without, in addition to all other requirements of this Code, having first paid to the City a "Utility Pavement Cut Recovery Fee." The Utility Pavement Cut Recovery Fee shall be due, as a condition of the permit required by Section 7-2.101.

Full Breakdown

101 requires a permit before anyone occupies, opens, tears up, breaks out, or excavates in any roadway, street, thoroughfare, sidewalk, parking strip, or public easement, whether for installing underground facilities, aboveground wiring on poles, or any other purpose, including publication vending machines. Applications go to the Director of Community Development and Services on City forms, with plans showing the work location, limits, pavement type, and replacement materials when the Director requests them. 103 lets the application follow on the next working day. 110 and become void if the work isn't finished by the date on the permit, unless the Director grants an extension for good cause.

No work is allowed in a newly paved street for three years after paving is completed except in circumstances beyond the permittee's control, and then only with mitigation such as a full pavement overlay. 101 permit, with the rate set by City Council resolution and adjusted annually to the Engineering News-Record construction cost index. The permittee must indemnify the City for injuries or property damage caused by the permitted work, and the Director may revoke a permit for noncompliance with the chapter.

Violations & Fines

The Community and Economic Development Director can revoke a permit under Section 7-2.112 for noncompliance with the encroachment chapter. If a permittee unduly delays the work, the City can step in and complete it under Section 7-2.209, charging the permittee its actual costs plus administrative expenses. Permittees also remain liable for any personal injury or property damage the work causes and must indemnify the City against related claims under Section 7-2.213.

Frequently Asked Questions

How far ahead do I need to apply for an encroachment permit in Pacifica?
Section 7-2.108 requires the permit to be secured at least two working days before work begins, except during an emergency street cut, opening or excavation, when Section 7-2.103 lets the application follow on the next working day instead.
Can I cut into a street the City just repaved?
No. Section 7-2.201(e) bars work in a newly paved street for three years after paving is completed, and if circumstances beyond the permittee's control force an exception, the City requires mitigation such as a full pavement overlay and additional base replacement.
What is the Utility Pavement Cut Recovery Fee?
It's a separate charge under Section 7-2.214 that anyone excavating in the public right-of-way must pay before the City issues the Section 7-2.101 permit, meant to recover the cost of pavement degradation caused by trench cuts, with the rate set by City Council resolution.

Sources & Official References

Other rules in Pacifica

All Pacifica rules

California rules heatmap·Compare Pacifica to another location·View the California sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Pacifica, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Encroachment Permits in Nearby Cities

How other cities in San Mateo County handle encroachment permits.

Redwood City, CA
Significant Restrictions