Key Facts

Permitting authority
Director of Development Services
Application lead time
48 hours before work starts
Security required
Deposit or bond for inspection/repair
Blanket permit term
12 months for utilities
Street cut moratorium
5 years after new construction
Penalty
Misdemeanor under § 1.12.010

Summary

San Bernardino requires a written encroachment permit before anyone excavates, obstructs, or puts a sidewalk, street, or public right-of-way to private use. The Director of Development Services issues the permit only after a 48-hour-advance application, a plat of the work, and a deposit covering inspection and repair costs.

It is unlawful for any person to make excavations or encroachments in or under the surface of any street, sidewalk or public place, for the installation, repair or removal of any pipe, conduit, duct or tunnel, or for any other purpose except the installation of poles and anchors serving overhead lines without first: (1) Making and filing a written application with the Director of Development Services a minimum of 48 hours prior to starting any excavation or encroachment...; (2) Receiving a written permit from the Director of Development Services; and (3) Making a deposit or other acceptable security to cover the cost of installation including: (a) Inspection; (b) Restoring the street or sidewalk to its original condition...

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-2: Supplement contains: Local legislation current through Ord. MC-1666, passed 8-5-2026).

Full Breakdown

020 defines ENCROACHMENT broadly: to encroach upon, obstruct, or close any public street, alley, court, sidewalk, or portion of it for any purpose, expressly including construction, parking, sales, advertising, or any private usage of public right-of-way. 060(C), it is unlawful to make an excavation or encroachment in or under a street, sidewalk, or public place for installing, repairing, or removing any pipe, conduit, duct, or tunnel, or for any other purpose except pole/anchor installation for overhead lines, without first filing a written application with the Director of Development Services at least 48 hours before starting work (utility franchise holders get next-business-day filing for emergencies), receiving a written permit, and posting a deposit or acceptable security covering inspection, restoration of the street or sidewalk to original condition, and incidental expenses.

060(D) requires the application to list the applicant's name and address, a detailed description and square footage of the work, and a scaled plat showing right-of-way lines, curb lines, underground utilities, and the trench dimensions. 070 sets a non-refundable right-of-way construction permit fee by council resolution, with a separate blanket permit (valid 12 months) available to public utilities for minor or emergency work. 100 adds a deposit before the permit issues to cover inspection, plan review, and repair/replacement, billed as a percentage of estimated construction cost.

055 also bars cutting a street surface within five years of city acceptance of new construction (three years for seal-coated or micro-surfaced streets) absent a Director exception.

Violations & Fines

Violating any provision of Chapter 12.03, including working without a permit or outside the approved plat, is a misdemeanor punishable under § 1.12.010, and the city may still pursue any other remedy allowed by law, such as ordering restoration work at the applicant's cost under § 12.03.130 or drawing on the posted deposit.

Frequently Asked Questions

Do I need a permit to place something on the sidewalk in front of my San Bernardino property?
Yes. Municipal Code § 12.03.020 defines encroachment to include any private usage of the public right-of-way, and § 12.03.060(C) makes it unlawful to encroach on a street, sidewalk, or public place without a written permit from the Director of Development Services.
How far in advance must I apply for an encroachment permit?
File a written application at least 48 hours before starting work under § 12.03.060(C)(1). Utility franchise holders may instead file the next business day for genuine emergency work.
What does the application need to include?
Under § 12.03.060(D), the application needs the applicant's name and address, a description and square footage of the work, and a scaled plat showing right-of-way lines, curb lines, and existing underground facilities.
Is there a fee to obtain the permit?
Yes. Section 12.03.070(A) requires a non-refundable right-of-way construction permit fee set by city council resolution, in addition to a separate deposit under § 12.03.100 to cover inspection and repair costs.

Sources & Official References

Other rules in San Bernardino

All San Bernardino rules

California rules heatmap·Compare San Bernardino to another location·View the California sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in San Bernardino, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Encroachment Permits in Nearby Cities

How other cities in San Bernardino County handle encroachment permits.

Fontana, CA
Some Restrictions
Rancho Cucamonga, CA
Some Restrictions
Ontario, CA
Some Restrictions
Chino, CA
Some Restrictions
Victorville, CA
Significant Restrictions
Rialto, CA
Significant Restrictions
Hesperia, CA
Significant Restrictions