Sandy Springs, GA Sidewalk & Pedestrian Rules: Encroachment Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit issuer
City of Sandy Springs Department of Public Works
Governs
Construction, driveways, permanent fixtures in right-of-way
Posting requirement
Permit must be posted at jobsite at all times
Restoration duty
Street and sidewalk restored to as-good-or-better condition
Penalty basis
General Code penalty under Section 1-10

Summary

Sandy Springs requires a right-of-way permit from the Department of Public Works before anyone builds a driveway, installs a permanent fixture, or performs construction work in a city street right-of-way. City Code Section 50-25 covers general construction, new driveway entrances onto public roads, and permanent features like signs, irrigation systems, or fences placed in the right-of-way.

(a)No person or company shall perform construction work in the street right-of-way without a permit issued by the city department of public works. Such permit is posted at the construction site at all times. Such construction must conform to the construction/maintenance guidelines and specifications of the city and/or the state department of transportation.(b)No person or company shall construct a drive or entrance to any public road without a permit from the city department of public works.(c)It is unlawful for any person to construct any permanent feature such as an irrigation system, sign or fence in the street right-of-way without a permit from the city department of public works.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 24 | Development Code: Supplement 2 | Technical Manuals: Supplement 4).

Full Breakdown

Article II of Chapter 50, 'Installation, Repairs and Maintenance,' governs any private use of the Sandy Springs right-of-way. Section 50-25(a) requires a permit from the city Department of Public Works before any person or company performs construction work in a street right-of-way, and the permit must be posted at the job site at all times, with work conforming to the city's or Georgia Department of Transportation's construction and maintenance guidelines. Section 50-25(b) separately requires a Public Works permit to construct a new driveway or entrance onto any public road, and Section 50-25(c) makes it unlawful to install any permanent feature, an irrigation system, sign, or fence, in the right-of-way without that permit.

Section 50-26 sets the application content: proposed measurements and plats of the work plus a signed statement attesting to compliance with local, state, and federal law, and lets Public Works add guidelines approved by the city manager. Section 50-27 requires the permit holder to post traffic control devices and signage under the Manual on Uniform Traffic Control Devices, and to erect guardrails and warning lights around any excavation. Section 50-28 obligates the permittee to restore the street, sidewalk, and landscaping to as-good-or-better condition once work is done, subject to a final Public Works inspection before the job is closed out.

Violations & Fines

Working in the right-of-way without a Section 50-25 permit, or leaving a posted permit off the jobsite, is punished under Section 50-24 per the general penalty in Section 1-10, which sets fines for city code violations. Public Works can also order restoration work redone if its final inspection under Section 50-28 finds the street, sidewalk, or landscaping was not returned to as-good-or-better condition.

Frequently Asked Questions

Do I need a permit to put a sign or fence in the Sandy Springs right-of-way?
Yes. Section 50-25(c) makes it unlawful to construct any permanent feature, including an irrigation system, sign, or fence, in the street right-of-way without a permit from the city Department of Public Works. This applies even on the strip fronting your own property, because the right-of-way itself remains public land under city control.
What has to be posted at the jobsite?
Section 50-25(a) requires the right-of-way construction permit itself to be posted at the construction site at all times, and Section 50-27 separately requires traffic control devices, signage, guardrails, and warning lights around any excavation to protect the public.
Who fixes the street after right-of-way work is finished?
The permit holder does. Section 50-28 requires the person or company that tore up the street, sidewalk, or landscaping to restore it to a condition as good as or better than before, and Public Works may run a final inspection to confirm the restoration before signing off.

Sources & Official References

Other rules in Sandy Springs

All Sandy Springs rules

Compare Sandy Springs to another location·View the Georgia sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Sandy Springs, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.