Walton County, GA Sidewalk & Pedestrian Rules: Encroachment Permits (2026)
Key Facts
- Permit required from
- Planning and Development Department
- Standard utility placement
- Back 5 feet of right-of-way
- Pavement cut repair window
- 24 hours
- Trench/bore pit clearance
- 10 feet from pavement edge
- Drawing size limit
- 11 x 17 inches
Summary
Any utility working within a Walton County right-of-way must first obtain a Utility Permit from the Planning and Development Department, pay the required fee, and submit detailed construction drawings. Most facilities must be installed within the back five feet of the right-of-way.
Section 10-2-190 - Utility Permit Requirements A.Any public or private utility proposing to construct, improve, relocate, repair, maintain or alter and utility system within any public right-of-way of Walton County, shall first complete and submit a Utility Permit Application for such activities to the Walton County Planning and Development Department for review and approval. ... 3.No pavement cuts shall be permitted without the prior approval of Walton County. All pavement cuts shall be repaired within twenty-four (24) hours, in accordance with the Standard Construction Details.4.No trench or bore pit shall be located closer than ten (10) feet from the edge of pavement, or at a distance of one (1) horizontal foot for each vertical feet of depth, whichever is greater.
Full Breakdown
Section 10-2-190 of the Walton County Land Development Ordinance requires any public or private utility that wants to construct, improve, relocate, repair, maintain or alter a utility system within a county right-of-way to first submit a completed Utility Permit Application to the Planning and Development Department for review and approval. The applicant must pay all applicable Utility Permit fees set by the Board of Commissioners to cover review and inspection costs, and must attach permit drawings no larger than eleven by seventeen inches showing the applicant's name and address, the road name and number, a description of the proposed work including size, type and length, the location relative to nearby intersections or landmarks, roadway and right-of-way dimensions, distance from the edge of pavement or curb, depth of cover, and a traffic control plan, among other listed items.
Once approved, installation must follow detailed standards: utilities generally go in the back five feet of the right-of-way unless the county approves otherwise, fixtures and manholes go at property corners where possible, no pavement cut proceeds without prior county approval and any cut must be repaired within twenty-four hours, trenches and bore pits must stay at least ten feet from the edge of pavement, and jack-and-bore road crossings need a welded steel casing extending ten feet on either side of the traveled surface. A Stop Work Order issues if the county inspector finds a contractor or utility company in violation of any part of these requirements during construction.
Violations & Fines
Performing utility work in a county right-of-way without an approved Utility Permit, making an unapproved pavement cut, or failing to repair an approved cut within twenty-four hours violates Section 10-2-190. The County Inspector can issue an immediate Stop Work Order halting all operations until the project comes into substantial compliance and further work is approved.
Frequently Asked Questions
Do I need a permit to install utility lines in a Walton County right-of-way?
Where in the right-of-way must utilities be installed?
How fast must a utility company repair a pavement cut?
Sources & Official References
Other rules in Walton County
Compare Walton County to another location·View the Georgia sidewalk & pedestrian rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.