Skip to main content
CityRuleLookup

Fountain, CO Sidewalk & Pedestrian Rules: Sidewalk Repair (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Fountain Municipal Code § 12.20.010
Who pays
Owner of abutting property
Notice period before city acts
30 days
Non-payment result
Special assessment lien
Original enactment
Ord. No. 28, 1905
State cross-reference
C.R.S. § 31-15-703

Summary

In Fountain, Colorado, the owner of property abutting a public sidewalk must build, rebuild, or repair that sidewalk at their own expense when the city council orders it. If the owner fails to act after written notice, the city's street commissioner or a contractor does the work and assesses the cost against the property as a lien.

Sidewalks shall be constructed by owners of property abutting on same, or at their expense, as provided in this chapter, throughout the city, in the manner provided for in section 12.20.020, and in such places and at such times as ordered by the city council.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 3).

Full Breakdown

020 and at the times and places ordered by the city council. 5 feet wide within that strip. 030 authorizes the street commissioner, under council direction, to build or repair the sidewalk instead. 040 requires the city clerk to serve the owner written notice giving 30 days to complete the work themselves, delivered personally or, for a non-resident owner or one who cannot be found, published for four weeks in the city's official paper. 070 requires the street and alley committee to inspect the finished work, report the cost to city council, and assess that cost as a lien against the abutting lot, collected the same as other property taxes if the owner doesn't pay directly. This chapter dates to the city's original 1905 ordinance (Ord. No. § 31-15-703.

Violations & Fines

There is no separate criminal penalty in this chapter; the consequence of an owner's failure to build or repair a sidewalk after 30 days' written notice is that the city performs the work through the street commissioner or a contractor and assesses the full cost, including inspection and administrative costs, as a special lien against the abutting property, collectible in the same manner as delinquent property taxes under § 12.20.070.

Frequently Asked Questions

Who has to fix a broken sidewalk in front of my Fountain house?
The owner of the abutting property does, at their own expense, under § 12.20.010, whenever the city council orders sidewalk work done in that location according to the specifications in § 12.20.020.
What happens if I ignore a Fountain sidewalk repair notice?
The city clerk gives the owner 30 days' written notice to complete the work under § 12.20.040. If the owner still doesn't act, the street commissioner or a city contractor builds or repairs the sidewalk and the full cost becomes a lien against the property, collected like other property taxes.
Does Fountain fund sidewalk repairs itself?
No. Section 12.20.010 makes sidewalk construction and repair the responsibility, and expense, of the abutting property owner; the city only steps in to perform the work directly after notice and non-compliance, and then bills the owner through a property lien.

Sources & Official References

Other rules in Fountain

All Fountain rules

Compare Fountain to another location·View the Colorado sidewalk & pedestrian rules overview

Get notified when Sidewalk Repair in Fountain, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Sidewalk Repair in Nearby Cities

How other cities in El Paso County handle sidewalk repair.

Colorado Springs, CO
Some Restrictions