Key Facts

Who is responsible
Owner of any lot fronting a public street, once the Board requires it
Trigger
Resolution of the Board of Mayor and Aldermen
Notice
Written notice from the city recorder, not less than 60 days
If owner refuses
City contracts the work; cost becomes a lien on the property
Construction permit
Director of public works; contractors must be bonded
Snow removal
Within six hours after snow stops, or by 10:00 a.m. if it fell overnight

Summary

In the City of Kingsport, Tennessee, the Board of Mayor and Aldermen can require the owner of any lot fronting a public street to build and keep in repair a good and substantial sidewalk along the whole street frontage. The owner gets written notice with at least 60 days to comply, or the city does the work and liens the lot.

The board of mayor and aldermen, whenever it is deemed necessary for the public welfare, may require the owner of any lot or part of lot in the city fronting upon any public street to construct and keep in repair a good and substantial sidewalk or travel way along the whole street frontage of his lot, of a width and materials prescribed by resolution of the board.

Full Breakdown

Section 90-162 gives the Board of Mayor and Aldermen the power, whenever it deems the action necessary for the public welfare, to require the owner of any lot or part of a lot fronting upon any public street to construct and keep in repair a good and substantial sidewalk or travel way along the whole street frontage, in a width and materials prescribed by resolution of the board. The duty starts with a resolution. Under § 90-163, the city recorder then gives the owner written notice stating the board's action, specifically setting out the work and the time allowed, and the time fixed cannot be less than 60 days.

If the owner refuses, § 90-164 lets the Board, through the city manager, contract for the construction or repair and pay the cost out of the street fund. From the date work begins, the cost is a lien on the property, equal in dignity to liens for the city property tax, enforceable by attachments at law or in equity or in the manner provided in the Charter, and the city attorney enforces it. Section 90-165 adds that the amount the city paid can be recovered from the owner by suit in any court of competent jurisdiction.

Work itself needs paperwork. Under § 90-160, no person constructs a sidewalk without a permit from the director of public works, and § 90-161 refuses that permit to any contractor who has not given the city a bond in the amount the Board determines. Day-to-day upkeep falls on occupants: § 90-49 requires the occupant of a house or lot with a permanent-material sidewalk to remove snow within six hours after it stops falling, or by 10:00 a.m. the next morning if it fell at night, and to remove or cover ice, sleet and mud. When there is no occupant, the duty falls on the owner. Under § 90-47, each first-floor business sweeps the paved sidewalk in front of the building before opening each morning except Sunday.

Violations & Fines

The enforcement tool in § 90-164 is a lien, not a fine: the cost of the city's contract work becomes a lien equal in dignity to city property tax liens from the date work is begun, and § 90-165 allows a suit to recover the amount. For snow and ice duties in § 90-49, the general penalty clause, § 1-14, sets a fine of not less than $10.00 or more than $50.00 unless otherwise provided, with each day a separate offense.

Frequently Asked Questions

Who has to repair the sidewalk in front of my Kingsport property?
You do, once the Board of Mayor and Aldermen requires it. Section 90-162 authorizes the Board to require the owner of any lot fronting upon any public street to construct and keep in repair a good and substantial sidewalk along the whole street frontage, in the width and materials the board prescribes by resolution.
How much time do I get to fix a sidewalk after notice?
At least 60 days. Under § 90-163, the city recorder gives written notice stating the board's action, the specific work to be done and the time allowed, and the time fixed cannot be less than 60 days. The notice follows a resolution of the Board of Mayor and Aldermen instructing you to construct or repair.
What if I refuse to repair the sidewalk?
Under § 90-164 the Board, through the city manager, can contract for the work and pay from the street fund. The cost becomes a lien on your property from the date work begins, equal in dignity to city property tax liens, and the city attorney enforces it. Section 90-165 also permits a suit to recover the money.
Who clears snow from a Kingsport sidewalk?
The occupant of the house or lot. Section 90-49 requires snow removed within six hours after it ceases falling, or by 10:00 a.m. the next morning if it fell during the night. Ice, sleet and mud must be removed or covered with sawdust, ashes or other safe material. With no occupant, the owner carries the duty.

Sources & Official References

Other rules in Kingsport

All Kingsport rules

Compare Kingsport to another location·View the Tennessee sidewalk & pedestrian rules overview

Get notified when Sidewalk Repair in Kingsport, TN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.