Key Facts

Governing section
Town of Clay Code Section 230-20H(3) and (6)
Tier 1 issuing authority
Town Code Officer only, no board review
Tier 1 systems covered
Roof-mounted and building-integrated panels
Tier 1 site plan review
Exempt in all zoning districts
Tier 2 contrast
Needs special use permit from Planning Board
Adopted
Local Law No. 1-2022

Summary

The Town of Clay's tiered solar rules at Code Section 230-20H let roof-mounted and building-integrated Tier 1 systems skip discretionary board review entirely. Permits for these systems are issued directly by the Town Code Officer and the system is exempt from site plan review, unlike ground-mounted Tier 2 systems that need a special use permit and Planning Board approval.

(a) Tier 1 solar energy systems include the following: [1] Roof-mounted solar energy systems. [2] Building-integrated solar energy systems. [3] Permits for all Tier 1 solar energy systems are issued by the Town Code Officer. (b) Tier 2 solar energy systems are residential or single building serving ground-mounted solar energy systems that are affixed to the ground either directly or by mounting devices and are not attached or affixed to a building or structure. All applications for Tier 2 solar energy systems are reviewed and approved or denied by the Town Planning Board. ... Permitting requirements for Tier I solar energy systems. All Tier I solar energy systems shall be permitted in all zoning districts and shall be exempt from site plan review under this section, subject to the following conditions for this type of solar energy system: ... [1] A solar/building permit and special use permit from the Planning Board shall be required for the installation of all ground-mounted solar energy systems.

Full Breakdown

Section 230-20H(3)(a) classifies roof-mounted and building-integrated solar energy systems as Tier 1 systems, and it states plainly that permits for all Tier 1 systems are issued by the Town Code Officer, without a special use permit or board hearing. Section 230-20H(6) confirms that all Tier 1 systems are permitted in every zoning district in the Town and are exempt from site plan review, though they still carry design conditions: panels on pitched roofs may sit no more than eight inches above the roof surface, must be mounted parallel to the roof, and cannot rise above the roof's highest point, while panels on flat roofs cannot extend above the surrounding parapet or more than 48 inches above the roof surface, whichever is higher, and all panels need an antireflective coating.

That contrasts with Tier 2 ground-mounted residential systems under Section 230-20H(3)(b) and (7), which require both a solar building permit and a special use permit from the Planning Board, are barred from front yards, need a 20,000-square-foot minimum lot, and face a 12-foot height cap, plus Planning Board screening conditions. Tier 3 systems, reserved for industrial and commercial zones under Section 230-20H(3)(c) and (8), go further still, requiring Town Board approval after a Planning Board advisory report and a public hearing with 10-day newspaper and mailed notice to neighbors within 400 feet.

Violations & Fines

Installing a Tier 1 roof-mounted or building-integrated solar system without the Code Officer's permit, or installing a ground-mounted Tier 2 system without the required special use permit from the Planning Board, is enforced as a zoning violation under Section 230-9: a fine of up to $750 or imprisonment up to 15 days, with each week of continued violation a separate offense.

Frequently Asked Questions

Can a Town of Clay resident get a rooftop solar permit without a board hearing?
Yes. Section 230-20H(3)(a) makes roof-mounted and building-integrated systems Tier 1, and permits for all Tier 1 systems are issued directly by the Town Code Officer with no Planning Board or Town Board review required.
Why does a ground-mounted solar system need more review than rooftop panels in Clay?
Ground-mounted residential systems are Tier 2 under Section 230-20H(3)(b), which requires a special use permit from the Planning Board, a 20,000-square-foot minimum lot and a 12-foot height cap, standards Tier 1 roof systems are exempt from under Section 230-20H(6).
Is a Tier 1 solar system exempt from site plan review in the Town of Clay?
Yes. Section 230-20H(6) states that all Tier 1 solar energy systems are permitted in every zoning district and are exempt from site plan review, subject only to the roof-mounting design conditions listed in that subsection.
What design limits still apply to an exempt Tier 1 rooftop system in Clay?
Section 230-20H(6)(a) requires pitched-roof panels to sit no more than eight inches above the roof, mounted parallel to it and no higher than its peak, flat-roof panels to stay within the parapet or 48 inches, and all panels to carry an antireflective coating.

Sources & Official References

Other rules in Clay

All Clay rules

New York rules heatmap·Compare Clay to another location·View the New York solar energy overview

Get notified when Expedited Solar Permitting in Clay, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.