Key Facts
- System size
- Up to 10 kilowatts AC or 30 kilowatts thermal
- Eligible buildings
- One- or two-family dwellings
- Review type
- Administrative and nondiscretionary, by the building official
- Submittal
- Email, internet or facsimile, with electronic signatures accepted
- Inspections
- One inspection by the building official
- Utility connection
- Not authorized by the permit; obtain from the utility
Summary
In the City of Pismo Beach, California, a small residential rooftop solar system of no more than 10 kilowatts alternating current or 30 kilowatts thermal gets an administrative, nondiscretionary permit review under Municipal Code § 15.12.010, with electronic submittal and a single inspection by the building official.
2. Small residential rooftop solar energy system. A solar energy system which meets all of the following: a. A solar energy system that is no larger than 10 kilowatts alternating current nameplate rating or 30 kilowatts thermal. ... ... 1. The building official shall establish an administrative, nondiscretionary expedited permit application review process for small residential rooftop solar energy systems, including standard plans and checklists. ... ... 4. A permit application for a small residential rooftop solar energy system shall be administratively reviewed and approved by the building official as a nondiscretionary permit within a reasonable time following receipt of a complete application that satisfies the requirements of the approved checklists and standard plans, and includes payment of all required permit processing and inspection fees. ... ... 1. Only one inspection shall be required and performed by the building official for small residential rooftop solar energy systems eligible for expedited review.
Full Breakdown
Section 15.12.010 defines a small residential rooftop solar energy system as one no larger than 10 kilowatts alternating current nameplate rating or 30 kilowatts thermal, installed on a one- or two-family dwelling, conforming to the applicable fire, structural, electrical and other building codes as adopted or amended by the city, with a panel or module array that does not exceed the maximum legal building height as defined by the city.
The building official must establish the expedited process, including standard plans and checklists that set out every requirement a system must meet to qualify. The process must substantially conform to the most current California Solar Permitting Guidebook adopted by the Governor's Office of Planning and Research, and the building official can modify the checklists for unique climactic, geological, seismological or topographical conditions. Checklists, standard plans and other permitting documents are posted on the City of Pismo Beach website.
An applicant can file by email, internet or facsimile, pay the permit processing and inspection fees as specified on the city website, and sign electronically. An application is complete when it satisfies the information requirements in the checklists and standard plans. If it is incomplete, the city sends a written correction notice detailing all deficiencies. A complete application is approved administratively by the building official as a nondiscretionary permit within a reasonable time. The building official can require a use permit if, based on substantial evidence, the system could have a specific, adverse impact upon public health and safety, meaning a significant, quantifiable, direct and unavoidable impact based on objective, written standards as they existed when the application was deemed complete. Approval shall not be based or conditioned on the approval of an association defined in section 4080 of the Civil Code, and it does not authorize connection to the local utility grid, which the applicant obtains from the utility.
Only one inspection is required and performed by the building official. A separate fire inspection can be performed if no agreement exists with the local fire code official to perform safety inspections on that official's behalf. If a system fails inspection, a subsequent inspection is authorized.
Violations & Fines
Section 15.12.010 prints no penalty clause of its own. Chapter 1.20 supplies the penalty. Under § 1.20.010 a violation of a city ordinance is a misdemeanor unless made an infraction, punishable by a fine of not more than one thousand dollars, imprisonment not to exceed six months, or both. Infraction fines are not exceeding one hundred dollars, two hundred dollars and five hundred dollars for a first, second and third or later violation within twelve months, and each day is a separate offense.
Frequently Asked Questions
How big can a rooftop solar system be for expedited review in Pismo Beach?
Can I submit a solar permit application online in the City of Pismo Beach?
Can the city demand a use permit for my rooftop solar system?
How many inspections does an expedited solar permit involve?
Sources & Official References
Other rules in Pismo Beach
California rules heatmap·Compare Pismo Beach to another location·View the California solar energy overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.