Key Facts

Qualifying PV system size
10 kilowatts AC or less
Qualifying thermal system size
30 kilowatts thermal or less
Plan check review time
1 to 3 business days (complete application)
Application options
In person or electronically (online)
Height limit
Must not exceed maximum legal building height

Summary

Unincorporated LA County offers an expedited permit process for small residential rooftop solar systems, with plan check review completed within 1 to 3 business days of a complete application.

City-specific rules exist: Carson, West Covina, Norwalk, Palmdale, Pomona, Pasadena, Downey, El Monte, Santa Clarita, Inglewood, Lancaster, Santa Monica, Los Angeles, and Long Beach have their own expedited solar permitting rules that differ from Los Angeles County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

SECTION 6801 - SCOPE: The provisions of this Chapter are intended to help the State of California reach its economic, energy and environmental goals by providing a standardized and streamlined permitting process to encourage the use of small residential rooftop solar energy systems. This Chapter shall apply to the permitting process for small residential rooftop solar energy systems...installed on a one- or two-family dwelling and involve either a photovoltaic system that is no larger than 10 kilowatts alternating current, or a solar thermal system for residential service water heating and solar pool heating that is no larger than 30 kilowatts thermal. SECTION 6803: Upon receipt of a complete small residential rooftop solar energy system application, plan check review will be completed within one to three business days.

Source: Gov Code §65850.5 / LACO 22.140.500View official code

Full Breakdown

Chapter 68 of Title 26 (Los Angeles County Building Code) establishes an expedited permitting process for small residential rooftop solar energy systems installed on one- or two-family dwellings. The streamlined process applies to photovoltaic systems no larger than 10 kilowatts AC or solar thermal systems for water heating no larger than 30 kilowatts thermal. Applications may be submitted in person or electronically. Once a complete application is received, plan check review must be completed within 1 to 3 business days. The installation must comply with the Solar Permitting Guidebook (Building Code Manual 6807, Article 1), and the panel array must not exceed the maximum legal building height. If the application is incomplete, a written correction notice is issued.

Violations & Fines

If a solar installation fails inspection, subsequent inspections are authorized until the work is approved. Installing a solar energy system without the required permit violates Section 103.1 of Title 26, making unpermitted work subject to a misdemeanor penalty of up to $1,000 or 6 months imprisonment, or both, per day of violation, plus investigation fees.

Frequently Asked Questions

How fast can I get a solar permit in unincorporated LA County?
For qualifying small residential rooftop solar systems (up to 10 kW PV), plan check review is completed within 1 to 3 business days of a complete application under Section 6803.
What size systems qualify for the expedited process?
Photovoltaic systems up to 10 kilowatts AC or solar thermal systems for water/pool heating up to 30 kilowatts thermal installed on a one- or two-family dwelling qualify under Chapter 68.
Can I apply for the solar permit online?
Yes. Section 6803 expressly allows applications to be submitted electronically through the online submittal system maintained by the Building Official.

Sources & Official References

Other rules in Los Angeles County

All Los Angeles County rules

California rules heatmap·Compare Los Angeles County to another location·View the California solar energy overview

Get notified when Expedited Solar Permitting in Los Angeles County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Expedited Solar Permitting in Cities Across Los Angeles County