Inglewood, CA Solar Energy: Expedited Solar Permitting (2026)
Key Facts
- System size cap
- 10 kW AC or 30 kW thermal
- Checklist adopted
- By September 30, 2015 (§ 11-170)
- Inspections
- Only one combined Building/Fire inspection
- Utility interconnection
- Separate approval from local utility required
- Appeal path
- Use-permit denial appealable to Planning Commission
- Enabling statute
- Government Code § 65850.5
Summary
Inglewood's Building Official issues small residential rooftop solar permits through a mandatory expedited checklist track for systems up to 10 kilowatts AC or 30 kilowatts thermal. Applications that meet every checklist item are deemed complete immediately; incomplete ones get a written correction notice, and eligible systems receive only one consolidated Building and Fire Department inspection.
(1) On or before September 30, 2015, the Building Official shall adopt an expedited permitting process for SRRSES, including a standard plan and checklist(s) of all requirements with which small residential SRRSES shall comply to be eligible for expedited review. (2) The checklist and all documents required for the submission of an expedited small residential SRRSES application shall be made available to the public on the City's website. (3) The fees prescribed for the permitting of small residential SRRSES shall be established from time to time by resolution of the City...and shall be located in the City's Master Fee Schedule...(5) An application that satisfies the information requirements in the checklist, as determined by the Building Official, shall be deemed complete. Upon receipt of an incomplete application, the Building Official shall issue a written correction notice detailing all deficiencies in the application and any additional information required to be eligible for expedited permit issuance.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4954608; v8 updated 2026-05-19).
Full Breakdown
5 for small residential rooftop solar energy systems (SRRSES). A qualifying system tops out at 10 kilowatts alternating current nameplate rating or 30 kilowatts thermal, sits on a single- or duplex-family dwelling or accessory structure, and stays within the maximum legal building height. Under Section 11-170, the Building Official adopted an expedited permitting process and standard checklist by September 30, 2015; that checklist and every required submission document is posted on the city's website so applicants can confirm eligibility before filing. Before submitting, the applicant must verify to the Building Official's satisfaction, through standard engineering evaluation, that the roof structure can carry the system's wind, seismic, dead and live loads, and must separately verify, at the applicant's cost, that the existing electrical panel and wiring can carry the new photovoltaic load.
55, 66015 and 66016 and Health and Safety Code Section 17951. An application meeting every checklist item is deemed complete on submission; the Building Official's approval under Section 11-171 authorizes installation and inspection but not utility interconnection, which the applicant must obtain separately from the local utility. Eligible SRRSES receive only one inspection, which can combine Building and Fire Department review; a failed inspection allows one follow-up inspection without the standard timing rule. If the Building Official finds substantial evidence of a specific, adverse health or safety impact, the applicant can be required to apply for a discretionary use permit instead, and that requirement or a denial of that use permit is appealable to the City Planning Commission.
Violations & Fines
Skipping items on the checklist does not block a permit outright, but an incomplete application draws a written correction notice from the Building Official listing every deficiency, delaying issuance until it is fixed. Energizing a system before the local utility approves interconnection is a separate step the city's permit does not authorize, and the applicant remains responsible for obtaining that utility sign-off. If the Building Official documents a specific, adverse safety impact, expedited review is revoked and a discretionary use permit is required instead.
Frequently Asked Questions
How fast can I get a solar permit in Inglewood?
Does Inglewood require more than one inspection for solar panels?
Can Inglewood deny my expedited solar permit?
Sources & Official References
Other rules in Inglewood
California rules heatmap·Compare Inglewood to another location·View the California solar energy overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Expedited Solar Permitting in Nearby Cities
How other cities in Los Angeles County handle expedited solar permitting.