Westminster, CA Solar Energy: Expedited Solar Permitting (2026)
Key Facts
- Permit issuance deadline
- 3 business days for complete applications
- Required inspections
- Only 1, scheduled within 2 business days
- Governing law
- Solar Rights Act + AB 2188 (2014)
- Adopted by
- Ordinance 2524, 2015, Chapter 15.06
- Appeal path
- Board of Appeals, § 15.04.025
Summary
Westminster runs an expedited, non-discretionary permitting track for small residential rooftop solar systems under Chapter 15.06, required by the state's Solar Rights Act and AB 2188. A complete application meeting the city's approved checklist gets a building permit within three business days, with only one inspection typically required.
The building department shall adopt an administrative, nondiscretionary review process to expedite the approval of small residential rooftop solar energy system applications within thirty days of adoption of this chapter. For an application for a small residential rooftop solar energy system that meets the requirements of the approved checklist and standard plan, the building department shall issue a building permit or other non-discretionary permit within three business days. The building official may require an applicant to apply for a use permit if the official finds, based on substantial evidence, that the solar energy system could have a specific, adverse impact upon the public health and safety. Such decisions may be appealed to the board of appeals pursuant to Section 15.04.025 of this code.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4982734; v10 updated 2026-06-10).
Full Breakdown
06, adopted by Ordinance 2524 in 2015, exists "to adopt an expedited, streamlined solar permitting process that complies with the Solar Rights Act and AB 2188 (Chapter 521, Statutes 2014)" for small residential rooftop solar energy systems. " Review is limited to whether the applicant meets local, state, and federal health and safety requirements, not broader discretionary design criteria. 025. 060(G) and (H), only one inspection is required and performed for systems eligible for expedited review, and that inspection must be scheduled within two business days of a request, with a follow-up inspection allowed if the system fails the first one.
Violations & Fines
Missing the checklist requirements does not create a fine; instead the application is deemed incomplete and the city sends a written correction notice under Section 15.06.060(F). Where the Building Official documents a specific adverse health or safety impact and requires a use permit, an applicant who proceeds with installation before that permit issues is subject to the same infraction/misdemeanor penalties as any other unpermitted building work under Section 205.1.
Frequently Asked Questions
How fast does Westminster issue a solar permit?
Can Westminster deny an expedited solar permit?
How many inspections will my solar installation get?
Sources & Official References
Other rules in Westminster
California rules heatmap·Compare Westminster to another location·View the California solar energy overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Expedited Solar Permitting in Nearby Cities
How other cities in Orange County handle expedited solar permitting.