Snohomish County, WA Solar Energy: Panel Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
SCC 30.50.103(3)(h)(ii)
Mechanical permit exempt
Single-family rooftop PV meeting 11 criteria
Electrical permit
Always required, no exception
Panel weight limit
3.5 to 5 psf depending on mount/slope
Max panel height
18 inches above roofing surface
Other systems
Construction permit under SCC 30.53A.332.44
Unpermitted work penalty
Investigation fee, SCC 30.50.162

Summary

Rooftop solar photovoltaic systems on detached single-family homes in unincorporated Snohomish County skip the mechanical permit if they meet the eleven-point checklist in SCC 30.50.103(3)(h)(ii): engineered mounting, roof-compliant weight limits, and proper flashing. Every system still needs an approved electrical permit, and larger or non-residential installations follow the standard construction permit process instead.

City-specific rules exist: Lynnwood, and Marysville have their own panel permits rules that differ from Snohomish County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

Specific to the residential code: ... (ii) Photovoltaic (PV) panels meeting all of the following criteria: (A) PV system is designed and proposed for a detached single-family house. (B) PV system is designed for the rooftop of a house in compliance with applicable codes... (E) PV system has an approved and issued electrical permit. (F) To address uplift, panels are mounted no higher than 18 inches above the surface of the roofing to which they are affixed, and except for flat roofs, no portion of the system may exceed the highest point of the roof. (G) Total dead load of panels, supports, mountings, raceways and all other appurtenances weigh no more than: (I) Three and one-half pounds per square foot (PSF)... (K) The house is code compliant with setbacks and height, or the code allows expansion of nonconformity for solar panels.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through legislation passed August 12, 2026).

Full Breakdown

103 lists work exempt from a construction permit, and subsection (3)(h)(ii) carves out rooftop photovoltaic panels on a detached single-family house from the mechanical permit only if the installation meets every listed criterion. The system must be engineered and designed for PV, mounted on a lightweight roof such as shingles, and installed with manufacturer-specified attachment and roof-penetration weatherproofing. To limit wind uplift, panels may sit no higher than 18 inches above the roofing surface and, except on flat roofs, no part of the array may exceed the roof's highest point.

Total dead load is capped at three and one-half pounds per square foot, rising to four and one-half pounds for frameless panels on a roof sloped at least three-in-twelve, and five pounds for frameless panels on at least a five-in-twelve slope, with the load spread across enough roof-framing members that no point carries more than 50 pounds. The house must also stay compliant with setback and height rules, or fall under a code allowance for expanding a nonconformity for solar. Criterion (E) requires an approved and issued electrical permit regardless of the mechanical exemption, so no PV installation in the county is entirely permit-free. 44, added by Amended Ordinance 21-031, effective July 25, 2021, which covers installing or modifying solar photovoltaic power systems.

Violations & Fines

Starting mechanical or electrical work on a solar installation before the required permit issues triggers an investigation penalty under SCC 30.50.162, billed per the hourly schedule in SCC 30.86.400(9) in addition to the standard permit fee. A rooftop system that misses even one of the eleven exemption criteria in SCC 30.50.103(3)(h)(ii), such as exceeding the weight or height limits, no longer qualifies for the mechanical-permit exemption and needs a full permit before work proceeds.

Frequently Asked Questions

Do I need a permit for rooftop solar panels in Snohomish County?
A mechanical permit isn't required for a detached single-family home's rooftop PV system if it meets all eleven criteria in SCC 30.50.103(3)(h)(ii), covering engineering, roof type, weight, height, and setbacks. An electrical permit is still mandatory in every case.
What if my solar system doesn't meet all eleven exemption criteria?
Then the mechanical-permit exemption doesn't apply, and the installation needs a standard building/mechanical permit. Larger, ground-mounted, or commercial systems fall under the fire code construction permit in SCC 30.53A.332.44 instead.
Is an electrical permit still needed if the mechanical permit is exempt?
Yes. Criterion (E) of SCC 30.50.103(3)(h)(ii) requires the PV system to have an approved and issued electrical permit regardless of whether the mechanical exemption applies, so no rooftop solar job in the county is entirely permit-free.
How heavy can my solar panel system be under the exemption?
SCC 30.50.103(3)(h)(ii)(G) caps total dead load at 3.5 pounds per square foot, rising to 4.5 psf for frameless panels on at least a 3-in-12 slope and 5 psf for frameless panels on at least a 5-in-12 slope, with load spread across roof framing.
What happens if I install solar panels before getting a permit?
SCC 30.50.162 makes anyone who starts permitted work before the permit issues subject to an investigation penalty billed under the hourly schedule in SCC 30.86.400(9), on top of the regular permit fee.

Sources & Official References

Other rules in Snohomish County

All Snohomish County rules

Compare Snohomish County to another location·View the Washington solar energy overview

Get notified when Panel Permits in Snohomish County, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.