Burleson, TX Solar Energy: Panel Permits (2026)
Key Facts
- Permit required
- Building permit before installation (§ 11-8)
- Installation standard
- Manufacturer's recommendations or Texas registered engineer's seal
- Roof system
- Permitted by right except PD and SP districts
- Ground system
- Minimum five acres, agricultural or industrial district only
- Tree penalty
- $2,000.00 per tree over six caliper inches removed without waiver
- Abandonment
- Out of service for a continuous six month period
Summary
In the City of Burleson, Texas, a building permit must be obtained before any solar panel system is installed. Under § 11-8 the equipment must follow the manufacturer's recommendations or a Texas engineer's seal, required landscape standards stay in force, and removing a tree over six caliper inches without a council waiver costs $2,000.00 per tree.
A building permit must be obtained prior to the installation of a sustainable energy device. Sustainable energy devices must be installed as per the manufacturer's recommendations or under the seal of a registered professional engineer in the State of Texas. The site must maintain required landscape standards at all times. A waiver will be required from city council to remove trees that are over six caliper inches from the site. The penalty for removing a tree without a waiver over six caliper inches will be assessed at $2,000.00 per tree removed over six caliper inches.
Full Breakdown
Chapter 11 of the Burleson Code of Ordinances, Sustainable Energy Devices, treats a solar panel system as a "sustainable energy device," and § 11-8 sets the permit step. A building permit must be obtained prior to installation. The device must be installed as per the manufacturer's recommendations or under the seal of a registered professional engineer in the State of Texas. The site must maintain required landscape standards at all times, and city council must grant a waiver before any tree over six caliper inches is removed from the site.
Where the panels go decides how hard the project is. Roof mounted systems are permitted by right in all zoning districts except PD and SP districts (§ 11-3). No more than six inches may separate the panel from the roof unless a waiver authorizes more, no part of the system can extend beyond the roof edges or roof ridge, and the design must prevent sun reflection toward vehicular traffic and any habitable portion of an adjacent structure. The fire marshal can require a specific roof location for safety.
Ground mounted systems are allowed by right only on tracts of at least five acres in the agricultural district (A) and industrial district (I), and are not permitted elsewhere in the city (§ 11-4). They are limited to 60 feet in height, installed in the rear yard only, and set at least 1,000 feet from interstate and state rights-of-way.
A waiver under § 11-9 is requested from the director of development with a nonrefundable filing fee. City council decides it after a public hearing, with written notice to owners of real property within 200 feet. After a denial, no other waiver request for the same tract or building is considered for six months. Section 11-10 treats a device out of service for a continuous six month period as abandoned: the owner gets 30 days to respond to a notice and 90 days to remove it after a determination of abandonment.
Violations & Fines
Section 11-8 prints one specific penalty: removing a tree over six caliper inches without the council waiver is assessed at $2,000.00 per tree removed. For an abandoned device, the city manager or designee can pursue legal action to have it removed at the owner's expense if the owner fails to remove it within 90 days of notice (§ 11-10). A waiver condition must be met before a certificate of occupancy is issued for the building (§ 11-9).
Frequently Asked Questions
Do I need a permit for rooftop solar panels in the City of Burleson?
How far can rooftop panels sit above the roof in Burleson?
Can I put a ground mounted solar array on a small residential lot in Burleson?
What happens if I need a tree removed for a solar installation?
Sources & Official References
Other rules in Burleson
Texas rules heatmap·Compare Burleson to another location·View the Texas solar energy overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.