Collierville, TN Solar Energy: Panel Permits (2026)
Key Facts
- Ground-mount height
- Not more than 14 feet
- Ground-mount lot coverage
- Less than 50% of the lot area
- Minimum distance
- Five feet from a property line or other building
- Rooftop height
- Not more than five feet above the finished roof
- Placement
- Behind the front facade of the structure
- Historic overlay
- Not readily visible from public view
Summary
In the Town of Collierville, § 151.025(D)(21) governs residential solar panels as an ancillary use. Ground-mounted cells top out at 14 feet and cover less than 50% of the lot, and rooftop cells cannot rise more than five feet above the finished roof.
(21) Solar panels. The use of ancillary use of photovoltaic (PV) cells to convert sunlight directly into electricity shall be regulated as follows. (a) Residential uses. 1. Ground-mounted PV cells shall: a. Not count towards the maximum of accessory structures permitted; b. Not located within easements or required buffer yards; c. Not exceed 14 feet in height; d. Are exempt from any screening requirements; e. Comprise less than 50% of the lot area; and, f. Be located behind the front facade of the structure have a setback from a property line that is equal to or greater than its height, or the required yard setback for the principal structure, whichever is less. In no case shall ground-mounted PV cells be located closer than five feet from a property line or other building or structure. 2. Rooftop residential PV cells shall: a. Not exceed five feet above the finished roof; and b. Are exempt from any rooftop equipment or mechanical system screening requirements: however, within the Local Historic Overlay PV cells shall be installed in locations that are not readily visible from public view to preserve the historic character of the property.
Full Breakdown
Collierville regulates photovoltaic cells as an ancillary use under § 151.025(D)(21), with separate standards for residential uses and for nonresidential and mixed-use properties. This record covers the residential standards, which split into ground-mounted and rooftop installations.
Ground-mounted PV cells on a residential lot cannot count towards the maximum of accessory structures permitted, cannot be located within easements or required buffer yards, and cannot exceed 14 feet in height. They are exempt from any screening requirements. They must comprise less than 50% of the lot area. They also have to sit behind the front facade of the structure, with a setback from a property line equal to or greater than the cell height, or the required yard setback for the principal structure, whichever is less. In no case can ground-mounted cells be located closer than five feet from a property line or other building or structure.
Rooftop residential PV cells cannot exceed five feet above the finished roof and are exempt from any rooftop equipment or mechanical system screening requirements. The exception to that exemption is the Local Historic Overlay: there, PV cells have to be installed in locations that are not readily visible from public view, to preserve the historic character of the property.
Nonresidential and mixed-use properties follow a different set: ground-mounted cells stay out of easements and buffer yards, comprise less than 50% of the lot area, sit behind the front facade and stay at least five feet from a property line or other building; rooftop cells cannot exceed ten feet above the finished roof and must be screened like rooftop equipment.
Large utility-scale solar is a separate matter. Electric production facilities are limited to photovoltaic cells under § 151.021 special conditions, and require a 25 acre minimum lot size and a decommissioning plan, so a rooftop or backyard array on a home falls under the § 151.025(D)(21) standards instead.
Violations & Fines
Installing or maintaining a structure or using land in violation of the zoning chapter is unlawful under § 151.998(B). A person convicted is subject to a fine, together with costs, up to the maximum limits established by law, and every day of violation is a separate offense. The Building Official takes written complaints, investigates, and can pursue legal action in court or seek injunctive relief against the installation.
Frequently Asked Questions
How tall can a ground-mounted solar array be at a Collierville home?
How close to the property line can ground-mounted panels go?
What are the rooftop solar limits in Collierville?
Do the residential rules differ from commercial solar rules in Collierville?
Sources & Official References
Other rules in Collierville
Compare Collierville to another location·View the Tennessee solar energy overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.