Pasco County, FL Solar Energy: Panel Permits (2026)
Key Facts
- Solar qualifies as single-trade work
- Solar energy and energy storage installations or alterations are named
- Notice of incomplete application
- 5 business days for one- or two-family single-trade review, otherwise 10
- If the county misses the deadline
- Permit is deemed approved and issues the next business day
- Private provider registration fee
- None; updates due within 5 business days of a change
- Provider insurance, project up to $5 million
- $1 million per occurrence, $2 million aggregate
- Audits of one provider
- No more than 4 per year, with 5 business days notice
- Certificate of completion on a one- or two-family home
- Issued or deficiencies noticed within 2 business days
Summary
Under Fla. Stat. § 553.791, solar energy and energy storage installations count as single-trade work, so a Pasco County property owner or contractor can hire a private provider to review plans and inspect the job. On a single-family or two-family home, the county has 5 business days to flag an incomplete solar permit application or the permit is deemed approved.
The term includes, but is not limited to, inspections or plans reviews of door or window replacements; fences and block walls more than 6 feet high from the top of the wall to the bottom of the footing; stucco or plastering; reroofing with no structural alteration; solar energy and energy storage installations or alterations; HVAC replacements; ... The local building official must provide written notice to a permit applicant of any incomplete forms or documents required under this section no later than 10 business days after receipt of a permit application or, if the permit application is relating to a single-trade plans review for a single-family or two-family dwelling, no later than 5 business days after receipt of a permit application, and an affidavit from the private provider as required in subsection (7). ... If the local building official does not provide such written notice within the prescribed time period, the permit must be deemed approved as a matter of law, and the permit must be issued by the local building official on the next business day.
Full Breakdown
Section 553.791 lets the fee owner of a Pasco County building, or the owner's contractor with written authorization from the owner, hire a private provider instead of waiting on county staff. The definition of single-trade work expressly lists solar energy and energy storage installations or alterations, so a rooftop array, a battery or an inverter swap qualifies for the private provider route. A private provider is a licensed building code administrator, engineer or architect. For residential additions and alterations of 1,000 square feet or less, a person holding a standard certificate under part XII of chapter 468 also qualifies.
The provider must register with the county before taking the job. The county cannot charge a fee for registering or updating, and the provider must update the registration within 5 business days of any change in contact information, licensure or insurance. The applicant notifies the building official in writing, on the Florida Building Commission's form, at the time of permit application or by 2 p.m. local time 2 business days before the first scheduled county inspection. The county cannot alter that form.
For plans review, the provider signs an affidavit under oath that the plans comply with the applicable codes. Single-trade reviews can use an automated or software-based system, and the county must accept electronically submitted affidavits. The building official reviews the paperwork for completeness only, plus local ordinances, floodplain management, site review and life safety items unrelated to the building code. Written notice of anything incomplete is due within 10 business days, or within 5 business days for a single-trade plans review on a single-family or two-family dwelling. Miss that deadline and the permit is deemed approved as a matter of law, to be issued on the next business day. If the provider is an engineer or architect who seals the affidavit, the official has 10 business days to issue the permit or cite the specific code chapters and sections that fail.
Pasco County cannot charge for plans review or inspections that a private provider performs, must cut the permit fee by the cost savings, and cannot add punitive administrative fees. After the inspections pass, the provider's firm issues a certificate of compliance, and on a one- or two-family home the county has 2 business days to issue the certificate of completion or name what is missing.
Violations & Fines
Section 553.791 sets no fine schedule for installers. Its penalties fall on the other parties. A building official who misses the 10 or 5 business day notice deadline loses the ability to hold the permit, which is deemed approved. On commercial projects, a county that does not cut fees by at least 25 percent, or 50 percent when a private provider handles everything, forfeits the right to collect any fees. A private provider answers to the disciplinary guidelines of the licensing board under chapters 468, 471 and 481.
Frequently Asked Questions
Can I use a private provider for a solar panel permit in Pasco County?
How fast must the county respond once a private provider's affidavit is filed?
Does Pasco County still charge plan review and inspection fees?
What insurance must the private provider carry?
What happens if the county and the private provider disagree?
Sources & Official References
Other rules in Pasco County