Skip to main content
CityRuleLookup

Davidson County, NC Solar Energy: Panel Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Construction permit fee
$100 flat fee, Appendix C
Legal basis
N.C. Fire Prevention Code construction permit, § 98.047(D)
Where to apply
Central Permitting or the Fire Marshal, § 98.049
Jurisdiction
unincorporated Davidson County only
Unauthorized work fee
double the normal permit fee

Summary

Davidson County's Fire Marshal treats a solar or photovoltaic power system as a permit-required construction item under the N.C. Fire Prevention Code. Chapter 98's Appendix C sets a flat $100 construction permit fee for Solar and Photovoltaic Power Systems, filed and reviewed through the same Central Permitting process as the county's other fire-code construction permits.

These county ordinances apply to unincorporated areas of Davidson County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

APPENDIX C - Required Construction Permits and Fees (continued)

Construction ... $100 Private Fire Hydrants $100 Smoke Control or Smoke Exhaust System $100 Solar and Photovoltaic Power Systems $100 Spraying/Dipping Operations $100 Standpipe System

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2024 S-15: Supplement contains: Local legislation current through Ordinance passed 4-22-2024; and State legislation through 2023 North Carolina Legislative Service, Pamphlet No. 6).

Full Breakdown

C. Fire Prevention Code in the unincorporated county. C. Fire Prevention Code requires its own separate permit and fee. Appendix C, titled 'Required Construction Permits and Fees,' lists Solar and Photovoltaic Power Systems at a $100 fee alongside other specialized fire-code construction categories such as battery systems, fire alarm and detection equipment, standpipe systems, and smoke control systems. 050. 058. Because Appendix C sits inside the Fire and Life Safety chapter, this $100 fee covers the fire-code construction permit for the solar or photovoltaic system itself; it does not describe any separate electrical or building permit that Central Permitting might also require for the installation under the county's Technical Codes.

Violations & Fines

Installing a solar or photovoltaic power system that requires a construction permit without first securing one is an unlawful act under § 98.073, and § 98.057 doubles the normal permit fee for work started before Central Permitting's approval or without the Code Official's knowledge. The Code Official can also issue a stop-work order under § 98.062, and § 98.999 authorizes civil penalties, equitable relief, or an injunction for continued noncompliance.

Frequently Asked Questions

How much does a solar panel permit cost in Davidson County?
Appendix C to Chapter 98 sets a flat $100 fee for a Solar and Photovoltaic Power Systems construction permit, the same fee structure used for other fire-code construction categories like battery systems and standpipe systems.
Who issues the solar permit?
Section 98.049 lets the applicant file through Central Permitting or directly with the Davidson County Fire Marshal, and § 98.047 governs the construction permit process under the N.C. Fire Prevention Code.
Does the $100 fee cover every permit a solar installation needs?
It covers the Chapter 98 fire-code construction permit for the solar or photovoltaic system specifically. The chapter does not describe any separate electrical or building permit Central Permitting may also require under the county's Technical Codes for the same installation.
What happens if I install a solar system without this permit?
Unpermitted construction covered by § 98.047 is an unlawful act under § 98.073, § 98.057 doubles the normal fee for unauthorized work, and the Code Official can issue a stop-work order under § 98.062 or pursue civil penalties under § 98.999.

Sources & Official References

Other rules in Davidson County

All Davidson County rules

Compare Davidson County to another location·View the North Carolina solar energy overview

Get notified when Panel Permits in Davidson County, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.