Greensboro, NC Solar Energy: Panel Permits (2026)
Key Facts
- Electrical permit required
- Yes, under § 6-111
- Fire prevention construction permit
- $150.00 (§ 10-10)
- Rebate available
- 50% of building & electrical fee
- Rebate cap, residential
- $40.00
- Rebate cap, commercial
- $80.00
Summary
Installing solar photovoltaic equipment in Greensboro requires both an electrical permit from the electrical inspector under § 6-111 and a $150 fire-prevention-bureau construction permit under § 10-10. The city offsets some of that cost with a 50% building/electrical fee rebate, capped at $40 residential or $80 commercial, under § 6-3.
Sec. 6-111. Permit and inspection required; exceptions. No electric wiring, devices, appliances or equipment shall be installed, within or on any building, structure, or premises, nor shall any alteration or addition be made in any such existing wiring, devices, appliances or equipment without first securing an electrical permit therefor and having an inspection thereof made by the electrical inspector... [Sec. 10-10, Construction Permit Fees:] Solar Photovoltaic Power Systems — Permit to construct — $150.00 — Per Permit. [Sec. 6-3:] Photovoltaic Energy Systems — Building Fee: 50% Rebate (not to exceed $40.00 residential or $80.00 commercial) — Electrical Fee: 50% Rebate (not to exceed $40.00 residential or $80.00 commercial).
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 132).
Full Breakdown
City Code § 6-111 requires an electrical permit and inspection before any electric wiring, devices, appliances, or equipment, which includes solar photovoltaic systems, are installed on or within a building, structure, or premises; only minor repairs like lamp replacement or utility-company work are exempt. 00 permit-to-construct fee, charged per permit, alongside the same fee structure used for gas detection systems, energy storage systems, and other fire-code-regulated construction. 00 for commercial projects. To qualify, all permit fees must be paid in full at issuance, the rebate application must be filed at the same time, the work must pass final inspection or receive a certificate of occupancy, and the system must be certified by the responsible third-party agency.
Because the city's separate Land Development Ordinance governs solar array siting and is not part of this Code of Ordinances download, this record covers only the permitting and fee mechanics found in the Code of Ordinances, not dimensional or zoning requirements for panel placement.
Violations & Fines
Installing photovoltaic wiring or equipment without first securing the required electrical permit is a violation of § 6-111, enforceable through the electrical inspector's condemnation and stop-work-order authority under §§ 6-99 and 6-100; failing to obtain a fire prevention bureau construction permit before beginning work triggers the chapter 10 civil penalty framework, including a $5,000 first-violation penalty for working without a required permit under § 10-5(a).
Frequently Asked Questions
Do I need a permit to install solar panels in Greensboro?
Can I get money back for installing solar in Greensboro?
Does the fee schedule cover where I can put solar panels?
Sources & Official References
Other rules in Greensboro
Compare Greensboro to another location·View the North Carolina solar energy overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Panel Permits in Nearby Cities
How other cities in this county handle panel permits.