Greensboro, NC Solar Energy: Panel Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Electrical permit required
Yes, under § 6-111
Fire prevention construction permit
$150.00 (§ 10-10)
Rebate available
50% of building & electrical fee
Rebate cap, residential
$40.00
Rebate cap, commercial
$80.00

Summary

Installing solar photovoltaic equipment in Greensboro requires both an electrical permit from the electrical inspector under § 6-111 and a $150 fire-prevention-bureau construction permit under § 10-10. The city offsets some of that cost with a 50% building/electrical fee rebate, capped at $40 residential or $80 commercial, under § 6-3.

Sec. 6-111. Permit and inspection required; exceptions. No electric wiring, devices, appliances or equipment shall be installed, within or on any building, structure, or premises, nor shall any alteration or addition be made in any such existing wiring, devices, appliances or equipment without first securing an electrical permit therefor and having an inspection thereof made by the electrical inspector... [Sec. 10-10, Construction Permit Fees:] Solar Photovoltaic Power Systems — Permit to construct — $150.00 — Per Permit. [Sec. 6-3:] Photovoltaic Energy Systems — Building Fee: 50% Rebate (not to exceed $40.00 residential or $80.00 commercial) — Electrical Fee: 50% Rebate (not to exceed $40.00 residential or $80.00 commercial).

Source: Greensboro Code of OrdinancesView official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 132).

Full Breakdown

City Code § 6-111 requires an electrical permit and inspection before any electric wiring, devices, appliances, or equipment, which includes solar photovoltaic systems, are installed on or within a building, structure, or premises; only minor repairs like lamp replacement or utility-company work are exempt. 00 permit-to-construct fee, charged per permit, alongside the same fee structure used for gas detection systems, energy storage systems, and other fire-code-regulated construction. 00 for commercial projects. To qualify, all permit fees must be paid in full at issuance, the rebate application must be filed at the same time, the work must pass final inspection or receive a certificate of occupancy, and the system must be certified by the responsible third-party agency.

Because the city's separate Land Development Ordinance governs solar array siting and is not part of this Code of Ordinances download, this record covers only the permitting and fee mechanics found in the Code of Ordinances, not dimensional or zoning requirements for panel placement.

Violations & Fines

Installing photovoltaic wiring or equipment without first securing the required electrical permit is a violation of § 6-111, enforceable through the electrical inspector's condemnation and stop-work-order authority under §§ 6-99 and 6-100; failing to obtain a fire prevention bureau construction permit before beginning work triggers the chapter 10 civil penalty framework, including a $5,000 first-violation penalty for working without a required permit under § 10-5(a).

Frequently Asked Questions

Do I need a permit to install solar panels in Greensboro?
Yes, two of them: an electrical permit and inspection from the electrical inspector under § 6-111, since photovoltaic equipment counts as electrical equipment, plus a $150.00 construction permit from the fire prevention bureau under § 10-10 for the solar photovoltaic power system itself.
Can I get money back for installing solar in Greensboro?
Yes. Under § 6-3's energy efficiency rebate program, a permit holder can recover 50 percent of the building permit fee and 50 percent of the electrical permit fee for a certified photovoltaic system, capped at $40.00 residential or $80.00 commercial, once the work passes final inspection and third-party certification.
Does the fee schedule cover where I can put solar panels?
No. The Code of Ordinances only sets permit and inspection fees; panel placement, setbacks, and height are governed by Greensboro's separate Land Development Ordinance, which isn't part of this code and must be checked separately.

Sources & Official References

Other rules in Greensboro

All Greensboro rules

Compare Greensboro to another location·View the North Carolina solar energy overview

Get notified when Panel Permits in Greensboro, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Panel Permits in Nearby Cities

How other cities in this county handle panel permits.

High Point, NC
Some Restrictions