Houston County, GA Solar Energy: Panel Permits (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Small Scale SES
under 5 acres footprint, no special permit
Intermediate Scale SES
5-50 acres, needs Special Use Permit
Large Scale SES
over 50 acres, needs Special Use Permit
Intermediate residential setback
50 feet from adjacent dwelling
Large Scale residential setback
150 feet from adjacent dwelling
Decommissioning deadline
starts within 12 months of shutdown

Summary

Unincorporated Houston County lets small ground-mounted solar arrays under 5 acres go in without a special permit, but any Intermediate (5-50 acre) or Large Scale (over 50 acre) system needs a Special Use Permit with a full site plan, visual buffer plan and decommissioning plan before the Governing Authority.

These county ordinances apply to unincorporated areas of Houston County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

A-105. Special Exception Application. In addition to the general requirements for a Special Exception application set forth in the County zoning code, the following shall be contained in any Special Use Permit application for an SES: A-105.1. Basic Information. The applicant shall submit a document that lists the following: A-105.1.1. the address of the property on which the SES will be located; A-105.1.2. the applicant's name, address, telephone number, and email address; A-105.1.3. the property owner's name, address, telephone number, and email address; A-105.1.4. if known, the SES operator's name, address, telephone number, and email address; A-105.1.5. if known, the installation company's name, address, telephone number, email address, and license number; and A-105.1.6. evidence of the applicant's control of the property, such as a deed, lease, or option agreement with the landowner.

Full Breakdown

Houston County's Comprehensive Land Development Regulations, Appendix A, split ground-mounted solar energy systems (SES) into three tiers by footprint: Small Scale (under 5 acres), Intermediate Scale (5 to 50 acres) and Large Scale (over 50 acres). 1, the appendix governs siting, construction, installation and decommissioning of any new SES built in unincorporated Houston County after its effective date; systems already operating are grandfathered unless their footprint grows more than 25 percent. Only Intermediate and Large Scale systems trigger the Special Exception/Special Use Permit process described in Sections A-105 and A-106.

1). 2). 3). 2 allows denial on stated grounds. Intermediate systems must sit at least 10 feet from a property line (or the district's own setback, whichever is greater) and 50 feet from any residential dwelling on an adjacent lot; Large Scale systems must sit at least 50 feet from any property line or right-of-way and 150 feet from a residential dwelling.

Violations & Fines

A violation of any provision of the Land Development Regulations, including Appendix A's SES permit requirements, is a misdemeanor under Section 161, prosecuted under Ga. Code Ann. § 69-9905, and each day the violation continues counts as a separate offense under § 69-1212. Installing an Intermediate or Large Scale system without the required Special Use Permit exposes the owner to daily citations until the system is brought into compliance or removed.

Frequently Asked Questions

Does a home rooftop solar panel need a county permit in Houston County?
Appendix A governs ground-mounted systems only; it defines Small, Intermediate and Large Scale by ground footprint acreage. A small residential rooftop array falls outside the ground-mounted tiers this appendix regulates, though normal building and electrical permitting still applies through the County's zoning code.
What size solar farm needs a Special Use Permit in Houston County?
Any Ground Mounted SES with a footprint of 5 acres or more, classified as Intermediate or Large Scale under Section A-100, must go through the Special Exception application in Sections A-105 and A-106 before the Governing Authority, including a decommissioning plan and liability insurance affidavit.
What happens to a solar farm once it stops operating?
Under Section A-102.5, decommissioning must begin no later than 12 months after the system stops generating power. A permit-free small system must be fully removed and the site restored within 6 months of decommissioning starting; a permitted system follows the decommissioning plan the County approved.

Sources & Official References

Other rules in Houston County

All Houston County rules

Compare Houston County to another location·View the Georgia solar energy overview

Get notified when Panel Permits in Houston County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.