Key Facts

Permit required
Yes, from chief building official
Connection
Barred until city authorizes
Fee
Per table, Sec. 9-47
Applies to
Solar thermal and photovoltaic systems

Summary

Solar thermal or photovoltaic installs in Midwest City need a building permit from the chief building official before any work begins.

Anyone desiring to erect, install, enlarge, alter, repair, remove, convert, or replace a solar thermal or photovoltaic solar system, the installation which is regulated by the adopted building codes of the City of Midwest City, or to cause such work to be performed, shall first make application and submit all required documentation as deemed necessary to the chief building official and obtain the required permits.(b)A person shall not make connections from a utility, source of energy, fuel or power to any building or system that is regulated by this Code until authorized by the chief building official.(c)See table located in section 9-47. (Ord. No. 3560, § 1, 4-23-24)

Secs. 9-165—9-184. - Reserved.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 21).

Full Breakdown

Anyone installing, enlarging, altering, repairing, removing, converting or replacing a solar thermal or photovoltaic system in Midwest City must first apply and submit required documentation to the chief building official and obtain a permit under the city's electrical code. No connection to a utility or power source is allowed until the chief building official authorizes it. Permit fees follow the fee table in § 9-47. This applies inside Midwest City limits, not on Tinker Air Force Base or in neighboring Oklahoma City, Del City, Choctaw, Nicoma Park or Spencer, which run their own permitting.

Violations & Fines

Connecting a solar system to power before city authorization violates § 9-158's connection-approval rule; working without a permit is a Code violation subject to the chief building official's enforcement and possible reinspection fees.

Frequently Asked Questions

Do I need a permit to install solar panels in Midwest City?
Yes. Section 9-164 requires an application and permit from the chief building official before installing, altering or replacing a solar thermal or photovoltaic system.
Can I connect my new solar system to the grid before inspection?
No. Section 9-164(b) bars connecting to a utility or power source until the chief building official authorizes it.

Sources & Official References

Other rules in Midwest City

All Midwest City rules

Compare Midwest City to another location·View the Oklahoma solar energy overview

Get notified when Panel Permits in Midwest City, OK changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.