Skip to main content
CityRuleLookup

Pageland, SC Solar Energy: Panel Permits (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Town Code App. A, Sec. 4-14
Where allowed
Conditional use, LI district only
Minimum setback
50 feet from property lines
Height limit
20 feet
Noise limit
50 decibels at property line
Permitting body
Zoning Administrator

Summary

Pageland's zoning table allows solar farm facilities only as a conditional use in the Light Industrial district, and Sec. 4-14 requires a zoning permit, sealed site plans, and a recorded decommissioning plan before one can be built.

A.Establishment. The establishment and operation of solar farm facilities shall comply with the following design and development standards:1.Site plans shall be prepared by a licensed land surveyor, landscape architect, or engineer. Plans must be sealed. ... 3.Setbacks. All ground-mounted solar farms must be set back a minimum of 50 feet from the edge of all property lines.4.Noise levels shall not exceed 50 decibels from the property line.5.Height. Solar structures shall not exceed 20 feet in height. ... B.Permitting process. Applicants shall apply to the Zoning Administrator and meet the following requirements:1.Complete and submit a zoning permit for a solar farm.2.Submit three site plans, scaled 11-inch by 17-inch or larger prepared by a licensed land surveyor, landscape architect, or engineer.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 1).

Full Breakdown

Sec. 4-14 of the Town of Pageland Zoning Ordinance sets design and permitting standards for solar farm facilities, the only solar use the Town's zoning table addresses; Table 1 lists it as a conditional use in the LI district and prohibited everywhere else in Town. Under Sec. 4-14(A), site plans must be prepared and sealed by a licensed land surveyor, landscape architect, or engineer, with easements addressed by Chesterfield County E-911 Addressing. Ground-mounted solar farms must be set back at least 50 feet from all property lines, cannot exceed 50 decibels of noise measured at the property line, and structures cannot exceed 20 feet in height.

The permitting process itself, laid out in Sec. 4-14(B), requires an applicant to submit a completed zoning permit application to the Zoning Administrator along with three site plans, sized 11 by 17 inches or larger, showing the developer's contact information, road layout, tax map reference, existing and proposed structures, property boundaries, adjacent land uses, and any nearby water bodies, floodplains, or wetlands with a 40-foot buffer identified. Approval further depends on a stormwater permit from SCDHEC for land disturbance of two acres or more, fire department review, a utility company agreement, and for facilities of 75 megawatts or more, South Carolina Public Service Commission approval. Sec. 4-14(A)(14) also requires a facility decommissioning plan recorded with the Chesterfield County Clerk of Court before the permit issues.

Violations & Fines

Building or expanding a ground-mounted solar facility in Pageland without the zoning permit, sealed site plans, and recorded decommissioning plan required by Sec. 4-14 is a zoning violation enforceable by the Zoning Administrator; expanding an existing grandfathered facility's footprint by more than five percent cumulatively over five years also triggers full compliance with the section.

Frequently Asked Questions

Where can a solar farm be built in Pageland?
Only in the LI, Light Industrial, zoning district, and only as a conditional use. Table 1 of the Zoning Ordinance marks solar farm facilities as not permitted in every other district in Town.
What permits does a solar farm need in Pageland?
Sec. 4-14(B) requires a zoning permit application to the Zoning Administrator, three sealed site plans, a stormwater permit from SCDHEC for two or more acres of land disturbance, fire department review, a utility company agreement, and PSC approval for facilities of 75 megawatts or more.
Does Pageland require a plan to remove a solar farm later?
Yes. Sec. 4-14(A)(14) requires a facility decommissioning plan covering the conditions and timeline for restoring the property, and that plan must be recorded in the Chesterfield County Clerk of Court's office.

Sources & Official References

Other rules in Pageland

All Pageland rules

Compare Pageland to another location·View the South Carolina solar energy overview

Get notified when Panel Permits in Pageland, SC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.