Plymouth, MN Solar Energy: Panel Permits (2026)
Key Facts
- Permit required
- Building permit under Section 21174.05
- Sloped-roof panel limit
- 2 feet above roof, within roof edges
- Flat-roof panel limit
- 10 feet above the roof section
- Ground-mount height limit
- 15 feet at maximum tilt
- Obsolete system removal
- Within 12 months of shutdown
- Applies to
- All zoning districts
Summary
The City of Plymouth allows solar energy systems in every zoning district but requires a building permit application backed by manufacturer spec sheets and to-scale drawings under City Code Section 21174.05. Roof-mounted panels on sloped roofs cannot extend more than two feet above the roof or beyond its edges, flat-roof systems cap at ten feet above the roof, and ground-mounted arrays cannot exceed 15 feet at maximum tilt.
21174.02. - Applicability.The solar energy system requirements of this Chapter shall apply within all zoning districts, except as otherwise provided herein. ... Subd. 1.Height and Arrangement. (a)Roof-mounted solar energy systems on sloped roofs: 1) shall have the same finished pitch as the roof; 2) shall not extend more than two feet above the roof section to which it is attached; 3) shall not extend beyond the boundaries of the roof; and 4) shall not extend above the peak of the roof section to which it is attached.( ... c)Ground-mounted solar energy systems shall not exceed 15 feet in height when oriented at maximum tilt. ... 21174.05. - Submittal requirements.An applicant for a solar energy system shall provide the following:Subd. 1.Information that demonstrates conformance to the requirements of this Section, as applicable.Subd. 2.Application materials required for a building permit.Subd. 3.Specification sheets and installation manuals for all manufactured components including, but not limited to, PV modules, inverter(s), combiner box, disconnects, and mounting system.
Full Breakdown
02 makes Plymouth's solar energy system rules apply within all zoning districts except as otherwise provided in the chapter. 03 sets height and arrangement standards for every installation: roof-mounted systems on sloped roofs must match the roof's finished pitch, cannot extend more than two feet above the roof section they are attached to, cannot extend beyond the roof's boundaries, and cannot rise above the roof peak; systems on flat roofs cannot extend more than ten feet above the roof section and cannot extend beyond the roof boundaries; ground-mounted systems cannot exceed 15 feet in height when oriented at maximum tilt.
04, though the Zoning Administrator can exclude them from lot coverage or impervious surface calculations. 05 requires the applicant to submit information demonstrating conformance with the chapter, the application materials required for a building permit, specification sheets and installation manuals for every manufactured component including PV modules, inverters, the combiner box, disconnects, and the mounting system, plus to-scale horizontal and vertical elevation drawings showing the system's location on the building for rooftop installs or on the property with dimensions from lot lines for ground-mounted installs.
Systems must be maintained under the property maintenance code, Section 405 of the City Code, cannot carry signage beyond required safety signage, and an obsolete system must be removed within 12 months of ceasing operation unless the Zoning Administrator grants an exemption.
Violations & Fines
Solar energy systems are inspected for compliance under the City's building permit process, and an obsolete or abandoned system left standing beyond the 12-month removal window without a Zoning Administrator exemption is a code violation subject to the City's standard enforcement and misdemeanor penalty provisions administered through the Building Official.
Frequently Asked Questions
Do I need a permit for solar panels in Plymouth?
How tall can a ground-mounted solar array be in Plymouth?
Can rooftop solar panels stick up above my roofline?
Sources & Official References
Other rules in Plymouth
Compare Plymouth to another location·View the Minnesota solar energy overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.