Key Facts

Ground-mounted zones allowed
B-4, I-L, I-Lb, I-M, I-Mb, I-H, A-B only
Ground-mounted height cap
20 ft above base of support
Minor system setback from RN/B-1/B-2
50 ft
Major system setback from RN/B-1/B-2
75 ft
Roof-mounted systems
excluded from height calculation
Governing section
LUC § 6.4.38

Summary

Portland's Land Use Code allows roof-mounted solar panels citywide without counting them toward maximum structure height, while ground-mounted systems are confined to the B-4, I-L, I-Lb, I-M, I-Mb, I-H, and A-B zones and capped at 20 feet, under § 6.4.38; major systems go through conditional-use review before a building permit issues.

6.4.38 Solar energy systems (major and minor) A. In general 1. All solar energy systems shall meet the technical, safety, and maintenance standards in the City of Portland Technical Manual. ... B. Ground-mounted solar energy systems 1. Ground-mounted solar energy systems are only permitted in the B-4, I-L, I-Lb, I-M, I-Mb, I-H, and A-B zones. ... 6. The absolute height of any ground-mounted solar energy system shall be no more than 20 feet above the ground as measured from the base of the support. ... C. Roof-mounted solar energy systems 1. Roof-mounted solar energy systems are not included in the calculation of maximum structure height.

View official code

Official source re-checked September 7, 2026: the cited page had not changed since it was quoted.

Full Breakdown

38 of the Land Use Code, effective July 1, 2026, sets the siting standards every solar installation must clear before the city issues a permit. All systems must meet the technical, safety, and maintenance standards in the City of Portland Technical Manual and must minimize construction and glare impacts on neighboring properties and roadways. Ground-mounted systems are the most restricted: subsection B confines them to seven zones, B-4, I-L, I-Lb, I-M, I-Mb, I-H, and A-B, and caps their absolute height at 20 feet above the base of the support, while minor ground-mounted systems must sit at least 50 feet from any RN zone and the B-1 and B-2/B-2b zones, and major ground-mounted systems must sit at least 75 feet from those same zones.

Roof-mounted systems get a lighter touch: subsection C exempts them from the calculation of maximum structure height, though flat-roof systems in residential zones are capped at 5 feet above the roof surface with a one-foot roof setback for every foot of height, and pitched-roof systems must mount parallel to and no higher than the roof surface. 4 authorizes only the filing and processing of applications for permits, including a building permit, before construction can begin.

Violations & Fines

Installing a ground-mounted solar energy system outside the seven zones listed in § 6.4.38(B), exceeding the 20-foot height cap, or building a major system without first securing conditional-use approval under § 6.5.6 is a zoning violation; roof-mounted systems that exceed the flat-roof height and setback standards in § 6.4.38(C) are likewise subject to code enforcement and can be required to be modified or removed.

Frequently Asked Questions

Where in Portland can I install a ground-mounted solar array?
Only in seven zones. Section 6.4.38(B)(1) of the Land Use Code limits ground-mounted solar energy systems to the B-4, I-L, I-Lb, I-M, I-Mb, I-H, and A-B zones, so residential and most business zones do not permit ground-mounted arrays at all.
Does a rooftop solar panel count against my building's maximum height in Portland?
No. Section 6.4.38(C)(1) excludes roof-mounted solar energy systems from the calculation of maximum structure height, though flat-roof systems in residential zones still can't exceed 5 feet above the roof surface, with a one-foot setback from the roof edge for every foot of panel height.
Do large solar installations need extra approval beyond a standard building permit in Portland?
Yes, if classified as a major system. Table 6 lists major solar energy systems as a conditional use cross-referenced to §§ 6.4.38 and 6.5.6, so the project must clear Article 6.5 conditional-use review, which authorizes applying for the building permit, before construction begins.

Sources & Official References

Other rules in Portland

All Portland rules

Compare Portland to another location·View the Maine solar energy overview

Get notified when Panel Permits in Portland, ME changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.