Key Facts

Governing section
TCC § 14.17.030 ([A]105.2, item 17)
Exempt if
Residential rooftop PV, complies with IRC M2301.2
Not exempt
Non-compliant or non-residential installations
Permit authority
Community Planning and Economic Development Dept.
No-permit penalty
Class 1 civil infraction, RCW 7.80

Summary

Thurston County does not require a building permit for a residential rooftop photovoltaic solar installation that complies with International Residential Code section M2301.2, per Code § 14.17.030 ([A]105.2, item 17). Fall outside that IRC section's requirements and the installation moves under the county's regular building-permit process.

These county ordinances apply to unincorporated areas of Thurston County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

[A] 105.2 Work exempt from permit. ... Permits shall not be required for the following: Building: ... 17. Residential photovoltaic roof top solar energy installations in compliance with IRC section M2301.2.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 77).

Full Breakdown

Item 17 of the exemption list in § 14.17.030, which amends International Building Code [A]105.2, excuses "residential photovoltaic roof top solar energy installations in compliance with IRC section M2301.2" from Thurston County's building-permit requirement. That exemption is conditional: it only reaches installations that meet the structural, fastening, and fire-clearance standards IRC M2301.2 sets for rooftop solar, so an installation that departs from those specifications, or one on a commercial or multifamily roof outside the residential code's scope, does not qualify.

An installation that falls outside IRC M2301.2's compliance path needs a permit under § 14.17.030's general rule, [A]105.1: the property owner or an authorized agent must apply to the Community Planning and Economic Development Department and secure a permit before mounting the array, and the fee for that permit follows the schedule adopted under § 14.17.050. Even an exempt installation is not excused from every county requirement: § 14.17.030 notes that exempt work can still need review under other chapters or under Titles 15 through 25 if the mounting affects roofing, structural load, or setbacks.

Installing a non-compliant rooftop system, or one that needs a permit and does not have one, exposes the owner to § 14.17.060's enforcement provisions: building without a permit under [A]105.1 is a class 1 civil infraction under Chapter 7.80 RCW, with each day of the violation treated as a separate infraction, backed by a misdemeanor penalty under [A]114.5 of up to $1,000, up to ninety days in jail, or both.

Violations & Fines

Installing a rooftop solar array that does not comply with IRC section M2301.2, or any other rooftop system that needs a permit under § 14.17.030 and lacks one, is a class 1 civil infraction under Chapter 7.80 RCW per § 14.17.060, with a separate infraction available for each day of continued unpermitted work and a misdemeanor exposure of up to $1,000 and 90 days in jail under [A]114.5.

Frequently Asked Questions

Do I need a permit to install solar panels on my roof in Thurston County?
Not if the installation is a residential rooftop photovoltaic system that complies with International Residential Code section M2301.2, per § 14.17.030's exemption list, item 17. An installation that does not meet IRC M2301.2's structural and fire-clearance standards, or one that is not on a residential roof, does not qualify for the exemption and needs a building permit.
What if my solar installation doesn't meet IRC M2301.2?
It falls under the general permit rule in § 14.17.030's [A]105.1. The property owner or an authorized agent must apply to the Community Planning and Economic Development Department and obtain a permit before mounting the array, with fees set under § 14.17.050 and the same one-year permit expiration that applies to other building work.
What's the penalty for installing solar panels without a required permit?
Section 14.17.060 makes building without a required permit a class 1 civil infraction under Chapter 7.80 RCW, with a new infraction available for each day the unpermitted work continues. The misdemeanor backstop under [A]114.5 adds exposure of up to $1,000 and ninety days in jail for continued violations.

Sources & Official References

Other rules in Thurston County

All Thurston County rules

Compare Thurston County to another location·View the Washington solar energy overview

Get notified when Panel Permits in Thurston County, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.