Walla Walla County, WA Solar Energy: Panel Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Ground-mount application fee
$75.00 (Code § 3.08.220)
Ground-mount permit fee
$205.00
Roof-mount permit fee
$155.00
Extra inspection fee
$80.00 each after first two
Building code basis
IRC + WA Energy Code, § 15.04.030
Commercial arrays
billed by project valuation, not flat fee

Summary

Installing a residential solar array in unincorporated Walla Walla County requires a Community Development building permit under the state energy code adopted at Code § 15.04.030. A ground-mounted array costs $75 to apply plus a $205 permit fee; a roof-mounted array costs $75 plus $155, both with plan review and $80 per inspection after the first two.

These county ordinances apply to unincorporated areas of Walla Walla County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Solar array, residential, ground mounted $75.00 application fee + $205.00 permit fee + plan review fee + $80.00 per inspection after first two Solar array, residential, roof mounted $75.00 application fee + $155.00 permit fee + plan review fee + $80.00 per inspection after first two ... There is adopted by the county of Walla Walla, state of Washington, the State Building Code, state of Washington, consisting of the current codes as adopted, amended or hereafter adopted and amended by the state: the International Building Code (IBC), International Residential Code (IRC), ICC/ANSI A117.1 Accessible and Usable Buildings and Facilities, International Mechanical Code, Liquefied Petroleum Gas Code (NFPA 58), National Fuel Gas Code for LP Gas (ANSI Z223/NFPA 54), International Fuel Gas Code, International Fire Code, Uniform Plumbing Code, International Existing Building Code, Washington State Energy Code and statutes which are adopted by reference by this chapter.

Full Breakdown

Walla Walla County Code § 3.08.220 sets separate flat fees for residential solar installations rather than pricing them off project valuation like most other building work. A ground-mounted residential array costs a $75.00 application fee plus a $205.00 permit fee, plan review fee, and $80.00 for each inspection beyond the first two. A roof-mounted residential array costs the same $75.00 application fee but only a $155.00 permit fee, plus the same plan review and per-inspection charges. Commercial and nonresidential solar arrays are not flat-fee; they are billed off project cost or building valuation using the county's standard valuation fee scale instead.

These fees sit inside the county's adopted State Building Code chapter, Section 15.04.030, which pulls in the International Building Code, International Residential Code, International Mechanical Code, International Fire Code, Uniform Plumbing Code and the Washington State Energy Code by reference for all unincorporated-area construction, including solar installations. Because a solar array is treated as building work under this chapter, it needs a Community Development plan review and permit before panels go up, not just a utility interconnection agreement. Applicants pay the $75 application fee at submittal, with the balance due before the permit issues, and any inspection beyond the two included in the base fee is billed separately at $80.00 each.

Violations & Fines

Walla Walla County treats solar installation as building work under the adopted state building and energy code at Section 15.04.030, so it needs a permit before installation, not just an electrical hookup. Each inspection beyond the two already included in the $205 ground-mount or $155 roof-mount permit fee costs an additional $80.00, and commercial or utility-scale arrays are billed off project valuation instead of the flat residential rate.

Frequently Asked Questions

Do I need a permit for rooftop solar panels in unincorporated Walla Walla County?
Yes. Walla Walla County treats a residential roof-mounted solar array as building work under the state energy and building code adopted at Code § 15.04.030, so Community Development requires a permit and plan review before installation, separate from any utility interconnection paperwork.
How much does a solar permit cost in Walla Walla County?
A ground-mounted residential array costs a $75.00 application fee plus a $205.00 permit fee under Code § 3.08.220, while a roof-mounted array costs the same $75.00 application fee plus a $155.00 permit fee. Both include plan review, with $80.00 charged for each inspection beyond the first two.
Are commercial solar arrays charged the same flat fee?
No. Code § 3.08.220 bills nonresidential and commercial solar arrays off project cost or building valuation using the county's standard valuation fee scale, rather than the flat $75 application and $155-$205 permit fees that apply to residential ground- and roof-mounted arrays.

Sources & Official References

Other rules in Walla Walla County

All Walla Walla County rules

Compare Walla Walla County to another location·View the Washington solar energy overview

Get notified when Panel Permits in Walla Walla County, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.