Fort Collins, CO Special Events & Permits: Commercial Filming on Public Right-of-Way (2026)

Light Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Threshold section
Sec. 23.5-3(b)(5)
Exempt if
No exclusive use or ROW closure
Otherwise requires
Full special event permit, Sec. 23.5-3(a)
Filing window if permit needed
45 business days
Other permits still apply
e.g., noise variance, Sec. 20-27

Summary

Commercial film production is legally one of Fort Collins's listed types of 'special event,' but Sec. 23.5-3(b)(5) carves out an exemption from the full permit: a shoot only needs a special event permit if it wants exclusive use of City property or a closure of a right-of-way normally open to the public.

(b)A special event permit shall not be required for the following:...(5)Commercial film productions that do not request exclusive use or closure of City-owned or managed buildings, plazas, property or land, and do not involve the obstruction or closure of any public rights-of-way that are normally open to the public.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Municipal Code: Supplement 155 | Transitional Land Use Code (for project before May 17, 2024): Supplement 61 | Traffic Code: Supplement 27).

Full Breakdown

Sec. 23.5-2 of the Municipal Code lists 'commercial film production' directly inside the definition of 'special event,' alongside block parties, parades and festivals, so on its face every film shoot on City property or in the right-of-way is covered by Chapter 23.5. Sec. 23.5-3(b) then lists categories exempt from the permit requirement, and (b)(5) removes 'commercial film productions that do not request exclusive use or closure of City-owned or managed buildings, plazas, property or land, and do not involve the obstruction or closure of any public rights-of-way that are normally open to the public.' That sentence is the dividing line City staff use to route a production down one of two tracks.

A shoot that just wants to film on a public sidewalk or in a City park without blocking anyone else's access falls outside the permit requirement and instead only needs the lighter notice process under Sec. 23.5-4.5. A shoot that wants a street closed, a plaza cleared, or exclusive use of a City building crosses into full special event territory under Sec. 23.5-3(a), triggering the standard 45-business-day filing window, insurance and deposit requirements under Sec. 23.5-5, a traffic safety plan requirement tied to the denial grounds in Sec.

23.5-7(4), and the right of appeal in Sec. 23.5-9. Productions that stay within the exemption are still not exempt from all City rules; Sec. 23.5-1 makes clear Chapter 23.5's requirements 'do not replace or substitute for other permitting requirements' such as a noise variance under Sec. 20-27, so a crew that avoids the special event permit by staying non-exclusive can still need other City sign-offs for the specific things it plans to do.

Violations & Fines

Misjudging which side of the Sec. 23.5-3(b)(5) line a shoot falls on carries real exposure: conducting a production that does require exclusive use or a right-of-way closure without first obtaining the full special event permit is unlawful under Sec. 23.5-12(a), the same violation that applies to any unpermitted special event, enforced through the general penalty at Sec. 1-15.

Frequently Asked Questions

Does filming a commercial in a Fort Collins park always need a special event permit?
No. Sec. 23.5-3(b)(5) exempts a commercial film production from the special event permit as long as it does not request exclusive use of City property or the closure of a public right-of-way that is normally open. It still must file the lighter notice required by Sec. 23.5-4.5.
What tips a film shoot into needing the full special event permit?
Requesting exclusive use of a City-owned building, plaza or land, or closing a public right-of-way that would otherwise stay open to the public, removes the Sec. 23.5-3(b)(5) exemption and puts the production on the standard special event track under Sec. 23.5-3(a), with its 45-business-day filing window.
If a film shoot is exempt from the special event permit, does it need any City approval at all?
Yes, potentially. Sec. 23.5-1 states Chapter 23.5's requirements do not replace other City permits, so an exempt shoot can still need approvals like a noise variance under Sec. 20-27 depending on what the production actually does.

Sources & Official References

Other rules in Fort Collins

All Fort Collins rules

Compare Fort Collins to another location·View the Colorado special events & permits overview

Get notified when Commercial Filming on Public Right-of-Way in Fort Collins, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.